Utilities 1423 results

UPDATE: 5-hour West Seattle Junction power outage

8:21 AM: Thanks for the tip! Seattle City Light’s map shows power out since 5:30 am to 425 customers in The Junction. No cause listed yet; we are checking with SCL.

8:32 AM: Just drove through the area: One sign of outage, 42nd/Alaska signal is dark.

9:31 AM: The Senior Center of West Seattle is partially out.

10:44 AM: As noted by commenters and confirmed by the map, power’s back. Julie Moore of SCL tells WSB a crow apparently caused it.

UPDATE: Another gas leak on Delridge Way

2:16 PM: Delridge Way is being shut down at Oregon because of a gas leak – second one on Delridge in less than a week. Updates to come.

2:26 PM: They’re closing traffic at Genesee on the north.

2:37 PM: Per radio exchange, the Community Center has been evacuated while firefighters continue taking air readings. This is several blocks south of last Friday’s problem.

2:46 PM: The gas leak is reported to have been “secured,” and Delridge will reopen shortly.

4:18 PM: Was SDOT’s contractor to blame? We asked. Reply: “The City and PSE are still investigating what caused today’s leak and will determine if there are any connections to a similar one in the area last week.”

Power outage in Westwood

Thanks for the tips. The Seattle City Light map shows 26 customers without electricity because of an outage in the Westwood Village vicinity. No word yet on the cause; though the map suggests a late-night restoration estimate, remember that those estimates are just guesses – could be a lot sooner or a lot later.

UPDATE: Gas leak at road-work site in 4000 block Delridge Way

(Part of the response. Photo by Erica, in comments)

9:52 AM: Avoid the 4000 block of Delridge Way SW – a major Seattle Fire response is arriving to help deal wth a gas leak at the road-construction site. Puget Sound Energy is there too.

9:57 AM: According to radio communication, three households have been evacuated.

10 AM: Also per a radio report to dispatchers, this will take some time to fix as repair crews have to excavate around the line. .. Traffic will be blocked to the north at Delridge/Spokane.

10:36 AM: Rough estimate: At least another hour. Meantime, some of the SFD units are being dismissed.

10:46 AM: The 5-way intersection camera, which was down for days, is back up.. Here’s what it’s showing for Delridge/Spokane.

10:56 AM: The leaking line has been shut down, dispatch was just told.

11:12 AM: The 5-way camera shows SB traffic is being allowed onto Delridge again. Per radio, they’re “opening everything up.”

UPDATE: Another Brace Point power outage

10:11 AM: Thanks for the tips. 337 customers south of Fauntleroy are out of electricity again. The same area lost power for a day and a half back in May. It went out around 8:30 this morning and is again attributed to “equipment failure.” As we reported in June, the area is scheduled for major work to replace its underground cabling, but the project has been delayed until early next year.

3:04 PM: Still out. We’re checking with City Light about the repairs’ status.

4:41 PM: Here’s how she replied:

This is the same location as the extended outage back in May in terms of customers impacted, but the issue is in a different area of the underground system. Crews have found the issue and have begun digging to reach it and make repairs. We expect this work will go well into the evening, potentially longer, before complete resolution.

Also, as you may have noticed on the outage map, the number of impacted customers has dropped from 337 to 43. This is because we were able to reroute service in a way that restored as many customers as possible while keeping necessary areas deenergized to safely make repairs. Please be aware that once repairs are complete, it is necessary to temporarily deenergize the broader area again to switch power back to the normal configuration.

UTILITY WORK: Seattle City Light installing overhead fiberoptic cables between local substations

Those two maps – top one between the South and Delridge substations, second one between the Delridge and Duwamish substations – show the routes for a fiberoptic-cable project Seattle City Light just announced:

Seattle City Light crews plan to install new fiberoptic cables between several utility substations in the southwest Seattle area. This work is needed to provide reliable communications for City Light’s electrical substations and operations network.

Beginning in mid-July 2020, City Light crews will pull overhead cables along several routes between the utility’s Delridge, Duwamish and South substations. Crews will be working on several utility poles to complete this work.

Additional Details:

Customers can anticipate temporary parking, sidewalk and traffic restrictions during this project. —

Flaggers will assist with directing traffic through work zones.

During this project, City Light will have the opportunity to upgrade infrastructure and replace utility poles that are in poor condition. Additional poles may be installed as well.

Some noise is expected from construction activities.

Maintenance power outages are not expected. If outages are needed, customers will be notified in advance.

The project will require rolling slowdowns on State Route (SR) 99 and SR 509. Details about this phase of work, tentatively beginning in September, will be shared with customers once a construction schedule has been determined.

This project is anticipated to start in mid-July 2020. Construction will last approximately two to three months. Construction work hours are from Mondays to Fridays, 7 a.m.-5 p.m. and weekends from 8 a.m.-5 p.m. Crews may be working outside these hours, as needed.

UPDATE: Power outage in south Morgan Junction/west Gatewood

9 PM: Thanks for the texted tip! 74 customers are without electricity right now in the south Morgan Junction/west Gatewood area, near California/Myrtle.

The City Light map says the cause is under investigation, but the texter reports a big clue – a dead crow.

9:55 PM: The City Light site now confirms “bird/animal” as the cause.

11:51 PM: Thanks to Sue for those tips plus word it’s over after four hours.

Water work south of The Junction

If you’re hearing construction-type noise – there’s a Seattle Public Utilities crew working on a water problem at California/Dawson, just south of The Junction. We haven’t heard from anyone whose water service has been affected, but did get a couple tips about the SPU crew (thank you).

FOLLOWUP: City finds ‘defect’ in sewer line near Alki slide site

(WSB photo, June 1st)

Two and a half weeks after a slide and water leak on the slope in the 1200 block of Alki SW – at which time Seattle Public Utilities told us the leak appeared to be on private property – an update from SPU spokesperson Sabrina Register:

On May 31, Seattle Public Utilities and Seattle Parks and Recreation responded to reports of a landslide from City property that affected private property at 1200 and 1210 Alki Ave SW. Staff have been working to assess whether the slide was the result of natural causes or caused by water. As moving water was found at the site, the City has been trying to determine the source of that water since the slide occurred.

Shortly after the slide occurred, SPU began checking upslope pipelines and systems for leaks and other damage and SPR evaluated the site for hazard trees. SPR will return to remove hazard trees when the site is made available. During its testing, SPU discovered a broken water service at one home above the slide zone, which was shut down. No other water leaks were discovered.

When the water outflow did not diminish, SPU continued to look for leak sources, including examining development patterns and their potential impact on drainage, and possible subsurface groundwater movement. SPU also conducted tests on water samples which showed elevated fecal coliform levels, indicating a possible sewer leak or another source such as animal waste.

Based on the fecal coliform levels, SPU had all upslope sewer mains inspected by CCTV. The inspection turned up a defect in a nearby 8- inch combined sewer line. While It is not currently known whether that defect is related to the landslide, SPU is planning for prompt repair of that sewer defect.

The Seattle Department of Construction and Inspections has dispatched Building inspectors to the site to evaluate the slope stability and the impacts to existing buildings and adjoining properties. No visible damage was observed.

We’ll be checking on the timeline for the promised repairs, as well as the building impacts.

FOLLOWUP: Seattle City Light project still planned for Brace Point, hit by 36+-hour power outage

June 15, 2020 4:20 pm
|    Comments Off on FOLLOWUP: Seattle City Light project still planned for Brace Point, hit by 36+-hour power outage
 |   Utilities | West Seattle news

Back on May 21-22, an underground-cable failure left hundreds of people south of Fauntleroy, mostly in the Brace Point area, without electricity for a day and a half. It wasn’t the first failure in the area. But it led to the question of whatever happened to a planned Seattle City Light project to fix the ongoing problems. We found some online documentation – such as the draft below, from early last year – which said the project was originally expected to start early this year.

Obviously, it didn’t. So we asked SCL about the project’s status. We got the reply today from spokesperson Julie Moore:

The Brace Point Cable Replacement Project is still active. It is in the project manual/specification preparation process for public work advertisement. The project was delayed during the project design development/SDOT permitting stage; that process took longer than originally expected. Construction is tentatively scheduled to start Q1 2021 and could last two years.

Brace Point property owners paid for the original underground project completed in the early 1970s (ordinance attached). As with such voluntary underground projects, the property owners pay for the initial installation and City Light is responsible for all maintenance, and in this case, the rebuild that should start next year.

A similar project in The Arroyos/south Arbor Heights has been under way for about two years.

City returns transfer stations to regular hours

Announced today by Seattle Public Utilities – the reduced schedule at transfer stations is over:

Seattle Public Utilities’ North and South Transfer Stations are open (as of June 15, 2020) normal operating hours, seven days a week from 8:00 am to 5:30 pm. We want to thank our customers for understanding that while the stations are operating at their normal schedule, that visits to the stations should be for essential trips only (urgent and perishable waste) in an effort to reduce potential spread of COVID-19.

For more on that, here’s the full SPU announcement. The South Transfer Station is just east of West Seattle, at 130 S. Kenyon.

RESUMING: Planned outages, for City Light projects requiring them

June 3, 2020 9:54 am
|    Comments Off on RESUMING: Planned outages, for City Light projects requiring them
 |   Coronavirus | Utilities | West Seattle news

Back in April, when checking on a notice received in one local neighborhood, we got first word that Seattle City Light was putting planned outages on hold. That’s ending, the utility has announced:

In April, as our community was observing Governor Inslee’s “Stay Home, Stay Healthy” order, City Light voluntarily paused all work that required an outage to minimize service disruptions to our customers.

Now, as we turn our attention to reopening and recovery, it’s critical that we resume essential critical infrastructure work to improve electrical reliability and ensure the safety of our infrastructure. Beginning June 8, we will resume critical work that requires planned outages.

Why Outages are Necessary

Planned power outages are important to maintaining and upgrading our infrastructure. Planned outages are necessary to ensure that City Light crews can complete their work in a safe, efficient manner. We understand that outages can be burdensome, and even more so as our customers are at home working, teaching children, and maintaining a healthy life during the COVID-19 crisis.

Planned outages are scheduled for a variety of reasons. Depending on the type of work, outages can occur during the day, at night or on the weekends. Our approach to scheduling planned outages is consistent throughout our service area. Safety, reliability and customer needs are considered as employees plan and schedule any outage-related work.

What Impacted Customers Should Expect

If a planned outage will be taking place in your neighborhood, you can expect to receive a notification at least five days ahead of the planned outage. The notification will be a door hanger, notice letter, or possibly an email for residential customers who live in an apartment complex or condominium building. The notification will contain detailed information about the planned outage, including the date, time, and anticipated duration of the outage. If an outage is cancelled or rescheduled (due to weather or other unforeseen circumstances), customers can expect to be notified about the change.

At this time, work will be moving forward for City Light’s Accelerated Pole Replacement Program. Crews are replacing aging utility poles throughout the utility’s service area to enhance safety and electrical reliability. For more information about this essential work and answers to frequently asked questions, please visit powerlines.seattle.gov/poles. Additional capital improvement projects and construction activities, including joint use work (e.g., telecommunications companies installing and maintaining equipment on our poles), will resume as work continues to restart across our service area.

To learn more about how you can prepare for an outage, please visit powerlines.seattle.gov/outage.

UTILITIES: About the pile of poles @ Hiawatha

Utility-pole replacements are of a bit more interest than usual ever since an old pole came down withuut warning in Morgan Junction two weeks ago. So we asked Seattle City Light about that delivery of poles on the east side of Hiawatha Community Center on Friday, after Rob Braby sent the photo. SCL’s Julie Moore just sent the info:

The poles are not for one job. The contractor will be replacing poles at multiple locations scattered around the vicinity. As a matter of efficiency, they simply delivered all the poles (actually, eight poles, I believe) at one time and left them on a public right-of-way in advance of work that will begin this week. Our pause in planned outages remains in place, so there will be no outages with this replacement work. The old poles will be tied to the new poles and we’ll return at a later time when we will take a temporary outage to transfer the equipment and remove the old pole.

FOLLOWUP: Day 2 of power outage in Brace Point area

12:12 PM: 34 hours and counting for that power outage we first mentioned Thursday morning. It started around 2:30 am Thursday with 160+ customers, and doubled before noon. Here’s the newest info from Seattle City Light‘s Julie Moore:

As I noted yesterday, it can take longer to find the issue in the underground system than with an overhead system. We’ve had crews onsite since the outage occurred and late yesterday morning we did locate the issue – a direct buried cable that went bad. Direct buried means just that – it is directly buried in the ground and not within conduit (this is an older system in this location; we no longer install systems in this manner). Unfortunately, the bad cable is also buried 8 feet under the road, which makes it more difficult to access.

The number of customers impacted increased from 165 to 337 because we needed to expand the outage to safely make the repairs.

The crews just tested the initial repairs and the fix is not fully complete. We have to do some more investigation of the cable. Crews will continue until restoration is complete.

8:50 PM: Liz commented about 45 minutes ago that she had power back; the City Light map shows the entire outage is now over. (If you’re still out, be sure to call SCL!)

UPDATE: Brace Point power outage

9:58 AM: Thanks to Jessica for the tip. 165 homes in the Brace Point area south of Fauntleroy are still out of power, after losing it in the middle of the night. We are checking with Seattle City Light about the cause. Xfinity service is also out in some if not all of the area, according to a tip from Nathan.

10:53 AM: SCL spokesperson Julie Moore tells WSB, “Crews are still investigating where the fault occurred. The neighborhood is fed through a underground residential distribution system, so crews are investigating each vault to see where the damage occurred and so they can identify the issue and make the repairs. This takes a bit more time than it does for an overhead system where it’s easier to pinpoint where damages occur along the power line or utility pole.”

12:14 PM: The SCL map now shows 337 customers out. (Thanks to Nathan for the alert on that.)

10:55 PM: Not fixed yet. Thanks to Hadlie for the photo (posted in comments) of SCL on scene. We’ll be following up again tomorrow.

10:56 WM: 12 hours later, still out – see comments for what neighbors are hearing.

12:13 PM FRIDAY: We’ve published a separate update.

UTILITIES: Emergency repairs ahead for West Seattle water main

5:17 PM: Just received this from Seattle Public Utilities:

Friday evening, May 22, Seattle Public Utilities will begin an emergency repair on a large, 16-inch water main that is leaking in West Seattle near SW Holly Street between California Ave SW and 39th Ave SW.

The repair work is expected to be completed by early Saturday morning, May 23, to avoid construction over the Memorial Day weekend.

In order to safely complete this work, crews must temporarily shut off water to about 65 homes in the area. Impacted customers will receive a door hanger from SPU on May 21 with information about the water outage, which starts at 9 pm on Friday, May 22 and ends at 5 am on Saturday, May 23.

The noisiest construction work will occur between 8 pm and 10 pm on May 22 when crews are breaking pavement to access the leaking water main. However, customers in the area may also experience some overnight noise while crews work to repair the pipe.

During the repair, if customers have questions about the work or their water service, they should contact SPU’s 24/7 Operations Response Center at 206-386-1800.

7:14 PM: We went over for a look and found the NO PARKING signs along Holly in the 41st/42nd vicinity, so looks like that’s expected to be the main work zone.

UPDATE: Power outage north of Schmitz Park

10:48 AM: Thanks for the tips. Seattle City Light is investigating an outage in the area shown on the map screengrab. 18 customers are affected, according to the SCL map, and have been without power for a bit over an hour.

11:54 AM: Outage over, reports Marc, who also sent that photo of a City Light truck wrapping up restoration work.

FOLLOWUP: Fallen Morgan Junction utility pole was ‘identified for replacement’

(Sunday night photo, sent by Beth)

11:56 PM: As promised, we followed up on the utility pole that spontaneously fell onto California SW between SW Graham and SW Raymond on Sunday night. As reported here, no one was hurt, but a car was damaged. Seattle City Light spokesperson Julie Moore tells WSB that pole had been “identified for replacement”; it was last inspected three years ago. “We are continuously inspecting poles, inspecting about 10% of our 92,000+ wooden poles per year,” Moore said. “This means we inspect each pole about every 10 years. Pole longevity can vary widely based on the wood species, treatment, and the environment where it is placed. A typical modern pole should last 40-60 years.” She also says that City Light has since checked 10 adjacent poles “as a precautionary measure” and “they all appear to be in good condition.”

P.S. If you see a pole with a clearly visible problem (leaning, etc.), info on how to report it is in this WSB story from a year ago.

1:41 PM: We asked for a bit more info on this pole’s history: “That pole was placed in 1953. Prior to 2017, it was inspected in 2010 and given a P5 rating, which is the top in our 1-5 rating system. Following the 2017 inspection, it was given a P2 rating, which is why it was identified for replacement.”

UTILITY ALERT: Emergency sewer repair

Seattle Public Utilities sent us a community notice late today about repair work that might already be under way, as it was scheduled to start as soon as this past Monday, but in case it hasn’t: The notice says at least six weeks of emergency work is ahead to fix a pipe in the alley “between 36th and 37th Ave SW and SW Stevens St and SW Hanford St.” Service interruptions are not expected, SPU says, but adjacennt residents “might be asked to limit water usage” at time. There’ll be noise, heavy equipment, and construction traffic in the area. The work is starting on the south side of the alley and will move to the north after two weeks or so. Here’s the official notice (PDF), which includes project-team contact info if you have questions/concerns.

UTILITIES: Planned power outage canceled

Earlier this week, we got a call from a reader concerned after receiving a Seattle City Light notice alerting to them for a planned daytime power outage later this week in Highland Park so a pole could be replaced. A 4-hour outage in the daytime might not have been a big hardship in the pre-pandemic days, but now a “residential” outage means cutting the power to many homes-turned-workplaces. So we asked SCL about it. Spokesperson Julie Moore tells WSB that the outage has been canceled and new notices about that were being taken around yesterday:

Seattle City Light remains committed to providing safe and reliable power while prioritizing the safety of our customers and crews. While important to maintaining and upgrading our infrastructure, we know planned outages can be burdensome, and even more so as our customers are at home working, teaching children, and maintaining a healthy life during the COVID-19 crisis. We’re temporarily adjusting our work to have the lowest impact on customers during this time.

As such, we are pausing all planned outages. Exceptions to this include emergency pole replacements where the work cannot safely be performed “hot”, emergency work necessary to restore service for customers who may be experiencing an outage, or to add a service connection for an essential facility (quarantine site, homeless shelter, etc.). As able, City Light will provide at least 48 hours advance notification for any of these situations.

Other pole replacement work will continue by placing new poles adjacent to poles in need of replacement and lashing them to the existing infrastructure, but we will wait until later to transfer services. City Light also will continue to do streetlight work and other work deemed essential as long as it does not require outages. Any work is in accordance with Governor Inslee’s Stay Home, Stay Healthy order and with protocols in place to meet all COVID-19 guidelines from the CDC, Washington Department of Health, and OSHA.

We will maintain this pause in planned outages at least through May 4, in alignment with the governor’s order. We recognize even as that order is lifted, many customers may continue to work or attend school from home. We will be thoughtful in our resumption of these activities, which are required to make repairs and upgrades to our infrastructure in a safe and efficient manner, and will do our best to work with customers to minimize impacts.

BROWN WATER: What to do if it happens to you

With everyone at home, more people might notice things such as discolored tap water. It happened to Jenny west of The Junction today, and she sent the photo. If it happens to you, here’s what to do:

Call Seattle Public Utilities at 206-386-1800.

They should be able to tell you whether it’s the result of a water-main break, or – as in Jenny’s situation – nearby hydrant testing. The latter often stirs up sediment (basically, rust) in the system, and that leads to tbe discoloration. After you’ve reported it, here’s what else to do.

This was so much of a problem a few years back that SPU did a major flush in West Seattle over the span of months in 2016 – read about it here. It’s important to let SPU know if you see it, because without so many reports back in 2016, they wouldn’t have done the flush.

POWER OUTAGE: 300+ customers, south of Fauntleroy

10 AM: Thanks for the tips. 330+ customers south of Fauntleroy, centered in Brace Point, are without power. About a quarter of them have been without it since last night; the rest lost it last night, got it back early today, and just lost it again. We are checking with City Light.

10:02 AM: Some just got it back again.

3:25 PM: Just in case you were wondering – outage map shows everyone back on.

Water break in High Point

Thanks for the tip. If you’re in the High Point area and without water service, that’s why – a break near the library. A Seattle Public Utilities crew is now on scene but has no estimate on how long repairs will take.