(SDOT photo: Structural-concrete work inside the bridge)
As first reported here on Tuesday, SDOT said the last two structural-concrete pours for the West Seattle Bridge repairs were scheduled for yesterday and today – and they’ve just announced that indeed, the last one did happen today. Here’s the announcement:
Today, our construction contractor finished pouring structural concrete inside the bridge, forming the structures that will hold new steel cables essential to strengthening the bridge. Completing this crucial project milestone marks the end of a challenging process that affected our reopening schedule.
We still expect to reopen the bridge in mid-2022 and can now work with our construction contractor to finalize the sequence of the remaining work.
Concrete work was originally scheduled to begin in February and was delayed by a concrete strike that affected practically every transportation and construction project in the Puget Sound region. We appreciate and thank the concrete suppliers and drivers who came together for the community to enable projects like the West Seattle Bridge to move forward again.
We never stopped working on the bridge, despite the concrete strike. We adjusted the sequence of work activities so that we could complete other strengthening measures like sealing cracks with epoxy and wrapping the bridge walls with carbon fiber.
This weekâs deliveries involved concrete trucks making back-to-back pours. Our construction contractor poured 15 truckloads of concrete in two days, more than half of the 245 cubic yards of structural concrete needed for the entire project.
The concrete was piped into the hollow bridge interior through a hole in the deck and was used to create massive blocks that form the foundations of the bridgeâs additional post-tensioning system. Once the concrete structures have cured after 28 days, theyâll be capable of holding more than 20 million pounds of force.
The next step in the post-tensioning process is to install ducts in the new concrete blocks so that we can thread steel cables through the length of the bridge. After the concrete has fully cured, we will tighten these cables to strengthen the bridge and prevent future cracking.
SDOT also confirmed earlier this week that it expects to present a reopening-timeframe update when the Community Task Force meets on June 9th.
| 32 COMMENTS