Update from Seattle Public Utilities: Repair work has finished early for the culvert that carries Pelly Creek and storm drainage to the outfall in the north section of the Lowman Beach Park seawall. The work started last Wednesday, was projected to last up to 10 working days, but was complete by this morning, according to Elaine Leung of SPU. Engineers will continue to survey the seawall weekly for the next few months.