(UPDATE: The county announced Friday that this won’t start until October 11)
(WSB photo looking into excavation site from Lincoln Park Way, taken today)
If you live near Lowman Beach, and/or along the routes that are being used by trucks to haul away dirt from the excavation for a million-gallon sewer-overflow tank, here’s an alert: Starting this Saturday, crews will be working on Saturday as well as weekdays, at least for this month. Here’s the announcement:
To keep the project on schedule and avoid digging during heavy rains, King County’s contractor will work Saturdays in October. Saturday work will begin at 9 a.m. and finish at 6 p.m. The County contractor expects to finish digging out the tank area by early November, before the largest winter storms usually arrive. Digging during storms takes longer and increases the chance of mud from the site getting on to streets and storm drains.
What to expect on Saturdays:
· Upcoming Saturday work days:
o October 4
o October 11
o October 18
o October 25· Work hours from 9 a.m. – 6 p.m. (Weekday work hours continue to be 7 a.m. to 6 p.m.)
· Noise from trucks and excavators, including backup alarms
· Excavators, pumps, and trucks working on and near the site
· Up to 55 trucks entering and leaving the site each day (about 7-8 trucks per hour)
· Flaggers to keep traffic moving as trucks access the site
· No parking on the eastern side of Beach Drive S.W.
· Limited parking on the western side of Beach Drive S.W.
· Limited access to the eastern sidewalk on Beach Drive S.W.
· Beach Drive S.W. and Lowman Beach Park remain open
· Primary haul routes remain Lincoln Park Way and 48th Ave N.W.
· The sound of running water may also be noticeable. Groundwater is being pumped from the tank area into a holding tank on site to allow for safe digging. The sound you may hear is typical for this kind of work.
The excavation work began two weeks ago – the report we published then includes the truck-hauling routes, if you aren’t familiar with them already.
| 14 COMMENTS