Spokane Street Viaduct: Sat. night closure; progress photos

(Photos courtesy Seattle Department of Transportation)
That’s one of the photos SDOT shared this week when we asked if they had any new construction-progress photos from the Spokane Street Viaduct Widening Project. We have a few more – but first, SDOT has just finalized plans for this weekend closure as part of the ongoing construction:

The Seattle Department of Transportation (SDOT) will close the westbound lanes of the Spokane Street Viaduct Saturday night, Oct 16, for work required on the viaduct widening project. (The Spokane Street Viaduct is the raised structure that connects the West Seattle Bridge to I-5.) Crews will work from 10 p.m. Saturday until 5 a.m. Sunday. During this work, southbound I-5 traffic will be directed to the South Forest Street exit to access surface streets. Northbound I-5 traffic and westbound traffic from South Columbian Way will be detoured to surface streets at Sixth Avenue South.

Note that this does NOT overlap with the Alaskan Way Viaduct closures this weekend, which are scheduled for 6 am-6 pm Saturday and Sunday. Meantime, three more views courtesy of SDOT:

As for the project’s overall status, according to SDOT’s Marybeth Turner: “The project remains on schedule for completion by spring 2012, with the new First Avenue on/off ramp complete by the fall of 2011.” Previous WSB coverage, dating back to the announcement of the Spokane Street Viaduct Widening Project in spring 2008, is archived here (newest to oldest).

5 Replies to "Spokane Street Viaduct: Sat. night closure; progress photos"

  • redblack October 15, 2010 (9:39 pm)

    thanks for sharing, TR. as much as i hate the whole road-building culture, i love to see impressive civic works like this one. and it’s a boon for west seattle.
    .
    love it or hate it, civil engineering is a fine art.

  • Momma Spice October 15, 2010 (10:02 pm)

    Decades overdue, but glad to see its being done.

  • Weattlite October 16, 2010 (1:32 am)

    Does that mean we won’t be able to come westbound from I-5 to West Seattle at all after 10 pm Saturday night?

    • WSB October 16, 2010 (1:34 am)

      Yes, closing that stretch of highway would indicate that ramp would be closed too …

  • Jordan October 16, 2010 (11:30 am)

    I’ve been very impressed with the speed they are getting it put up. Still a year and a half away to completion, but it should really help things.

    Thanks for the updates!!