FAUNTLEROY BOULEVARD PROJECT: Community group’s 2nd meeting planned

2016_nov_fauntleroy60_planview

One month ago today, we published our report on the launch meeting of the Fauntleroy Way Neighborhood and Business Association, formed out of concerns related to the years-in-the-works, in-final-design-phase Fauntleroy Boulevard project. The group has just announced its second meeting, 7:30 pm Wednesday, April 19th, with a list of current/continuing questions and concerns:

The Fauntleroy Way Neighborhood and Business Association will host this meeting to discuss the current status of the Fauntleroy Way Boulevard project. Our aim is to leave this meeting with a clearer understanding of the project with respect to the following Association interests:

PROJECT DESIGN

Traffic studies. Per SDOT, a new traffic study was ordered. Our requests for an update have gone unanswered, to date.

Current design completion. We were informed the design is now at 90%, but have not received updates from the SDOT mailing list, from SDOT directly, or how any traffic study may have impacted design updates.

Treed medians vs. left turn lanes. SDOT indicated that they were re-examining additional access along Fauntleroy Way in place of planned treed medians, but we have received no update, to date.

Addition of crosswalks. Much of the justification for this project relates to pedestrian safety, but no additional crosswalks are planned. At our last meeting with SDOT, we were told this was being examined, but we have received no update, to date.

Loading zones and temporary parking. Will there be any spaces along the street that allow for short-term parking, e.g. 3-minute loading and unloading.

DURING CONSTRUCTION

Construction worker parking. Given the squeeze on existing parking in the area, will workers be made to park outside the area of affected business to allow greater access by our patrons?

Communication of the project to the neighborhood. What is SDOT’s plan for communicating traffic plans to the West Seattle community? Businesses would like some say in the way this is communicated to help keep our doors open.

Signage for businesses during construction. We’ve been advised by OED that this is normally not planned for. Given the extended duration of this project, we would like to reach a compromise.

Pedestrian access. Will pedestrians have access to the length of Fauntleroy Way throughout construction?

Mitigation. We have been advised by OED that the only mitigating assistance the City will provide to impacted businesses will be in the form of access to construction updates and influence on project phasing and planning. We seek more clarity around this so that we can plan ahead to work together.

Traffic re-routing plan. We would like any update available on the planned traffic re-routing during construction. Per the note on mitigation, our strong preference would be to keep traffic moving in both directions along Fauntleroy Way for the length of the project.

23rd Project. What has SDOT/the City learned from the 23rd Ave project that will positively impact the Fauntleroy Way project?

Please contact us with any questions or concerns:
Fauntleroy Way Neighborhood and Business Association fauntleroywayassoc@gmail.com

The April 19th meeting will be in the Rotary Room at the West Seattle YMCA (36th/Snoqualmie; WSB sponsor).

1 Reply to "FAUNTLEROY BOULEVARD PROJECT: Community group's 2nd meeting planned"

  • brian April 7, 2017 (7:43 am)

    I see that cycle track and it warms my heart. YES PLEASE.            

Sorry, comment time is over.