ORIGINAL REPORT, 12:13 PM: Just in from WSDOT:
The Alaskan Way Viaduct Replacement Program (WSDOT) is in the process of notifying Seattle Tunnel Partners to suspend tunneling operations involving the tunnel boring machine, a “Suspension for Cause” in contractual terms, until such time as WSDOT lifts the suspension in writing. We will provide a copy of the letter after it is delivered to STP.
The following is a statement from Secretary of Transportation Lynn Peterson:
“In light of recent incidents on the SR 99 Tunnel Project, WSDOT is notifying the contractor that they must suspend tunneling work for cause. I share the Governor’s concern for public safety and we want to ensure that the contractor has the right protocols in place to proceed with their work safely.
We are asking that the contractor complete root cause analysis and take the appropriate steps to ensure that incidents, such as the sinkhole near the repair pit, do not occur again. STP will not be allowed to resume tunneling until their analysis and work plans meet the satisfaction of our experts.
I want to remind everyone that replacing the viaduct is critical to public safety. We have conducted surveys of the viaduct and no movement has been observed; surveys will continue. The tunneling work must proceed, but it must proceed safely.”
This week alone, besides the 35′ x 20′ x 15′ sinkhole, there also was trouble with the barge being used for excavation spoils. WSDOT stresses, however, that other work – such as the Highway 99 lane closures starting next week for tunnel-related sign installation – goes on. More as we get it. Per WSDOT’s “Follow Bertha” page, as of Tuesday, 1,280 feet of tunneling had been completed, of 9,270 feet in all.
P.S. Checking our archives – available via Google cache until our full site is up – we note that yesterday was the seventh anniversary of the announcement by then-Gov. Gregoire, then-Mayor Nickels, and then-County Executive Sims that a deep-bore tunnel had been chosen to replace the Alaskan Way Viaduct.
4:02 PM UPDATE: As promised, WSDOT has made public the letter sent to Seattle Tunnel Partners. You can read it in its entirety here. Here’s what’s at the heart of it:
WSDOT has determined that STP has failed to correct conditions unsafe for the Project personnel or general public, and failed to comply with Governmental Approvals, Law, or otherwise carry out the requirements of the Contract Documents. Therefore, WSDOT has the authority to suspend work for cause, pursuant to Contract Sections 14.2 (a) and 14.2(b) and Technical Requirements Section 2.52.7.3.5.
On the night of January 12, 2016, a sinkhole was detected over the tunnel. The full extent of ground loss is not yet determined and settlement is increasing. STP has yet to provide a detailed analysis of the cause of the observed ground settlement, or a plan for modifying tunneling operations to ensure positive ground control at all stages of tunneling (TR 2.32), and to prevent settlement outside of tolerance in the future (see TR 2.52).
On Tuesday January 12, 201 6, STP’s barge filling operation resulted in a barge listing beyond STP’s control. As a result the barge was either let go or broke free from the pier, spilling tunnel spoils into Elliott Bay, and drifted out of control damaging both Terminal 46 and Pier 48. These events created an unpermitted spill of material and posed a hazard to project personnel and the public.
WSDOT requests a meeting with STP within 24 hours to address this matter.
| 6 COMMENTS