![](https://westseattleblog.com/blog/wp-content/uploads/2015/03/ah31215-e1426282217675.jpg)
(WSB photo, taken this week, looking southwest across the AHES site)
Someone asked us why the Arbor Heights Elementary rebuild site is idle. That’s by design – as reported several times before, this was intended to be a two-phase project, with demolition/site prep in the first phase, and then a stopdown while the full construction project went out to bid. We checked in with Seattle Public Schools today and confirmed that Bayley Construction is the winning bidder, for $25.4 million; the contract is expected to be awarded within a few weeks, likely going to the School Board on April 1st. If all goes as planned, work at the site is expected to (re)start in early May, though the district tells us neighbors might see some activity – such as “trailer mobilization” – before then. The new school is expected to open in fall of 2016; AH continues using part of the Boren Building as its temporary site until then.
| 4 COMMENTS