(UPDATED LATE WEDNESDAY AFTERNOON with progress report)

9:47 AM: Last week, WSDOT said the Highway 99 tunnel contractor would likely start the process this week of trying to get the tunneling machine to move 20 feet ahead so its damaged cutterhead can be pulled from the 120-foot-deep pit dug next to the Viaduct. This morning, there’s word the process has begun. As of 7 this morning, according to WSDOT’s announcement, the machine had made it about three feet forward:
The machine must mine through 20 feet of unreinforced concrete to reach the pit. The duration of this effort will depend on the machineâs ability to mine through the concrete while operating with a damaged seal system. STP anticipates the machine may overheat, as it has during their most recent attempts at mining. If the machine becomes too hot, they will take a break for it to cool down before resuming.
The image above is from the WSDOT page displaying several “live” construction cameras. (P.S. The south side of the pit, where it’s expected to break through, is on the left side of the photo.)
4:32 PM: WSDOT has just posted another update – saying the machine has now gone six feet.
| 14 COMMENTS