Bridge updates as we start the holiday-shortened workweek:
CITY COUNCIL VOTES ON FUNDING: The plan for $70 million in “interfund” loans to finance the first stage of West Seattle Bridge work gets a final vote when councilmembers reconvene today after the two-week end-of-summer recess. This won unanimous Transportation Committee approval before the recess. More info is in the 2 pm meeting agenda.
BRIDGE STABILIZATION UPDATE: In case you haven’t seen this already, SDOT has published its second end-of-week update on the stabilization work, including this:
(This) week, the contractor is planning to:
(SDOT photo, on one of the under-bridge platforms)
-Complete the first phase of filling cracks with epoxy.
-Begin the second phase of crack injection towards the middle of the bridge.
-Continue to inspect cracks.
-Place carbon fiber wrap around recently filled cracks.
-Continue installing the post tensioning system.During this work, you’ll see:
-Some crews working on top of and under the bridge.
-Scaffolding and crews working on platforms suspended under the bridge.There’s additional work taking place inside the bridge – including monitoring cracks and preparing for the installation of additional post-tensioning strands – that you will not be able to see.
COMMUNITY TASK FORCE MEETS: 3 weeks after its last meeting, the West Seattle Bridge Community Task Force meets online Wednesday at noon. We hope to get the agenda and connection information from SDOT later today, but in the meantime, one known agenda item: The Reconnect West Seattle implementation plan. We’ve previewed the draft, and among other things, SDOT has slight revisions in the.mode-shift commuting goals – increasing the percentage of commutes it hopes will be made by bicycle next year to 10 percent, for one example (last year’s baseline was 1 percent):
In the 2019 Baseline, about 60 bicycles crossed the Duwamish per AM peak hour. The Lower Spokane Bridge can accommodate 400 – 1,000 bicycles per hour. To accommodate 1,000 bicycles per AM peak hour, SDOT will need to make substantive capital improvements across West Seattle.
The Reconnect WS plan has separate bicycle and freight sub-plans as well as four project lists for the areas most affected by bridge-detour traffic.
12:30 PM UPDATE: Here’s the link for watching tomorrow’s meeting, or use access code: 146 544 1172 after calling 408-418-9388.
AUDIT OF OTHER BRIDGES: Right after the sudden bridge shutdown took so many by surprise 5 1/2 months ago, Councilmember Alex Pedersen – who chairs the Transportation Committee – called for an audit of the city’s other bridges, to be sure no other surprises are lurking. He announced in this online update that the audit will be presented to his committee next week, on September 16th.