If you live, work, and/or have traveled along the north half-plus of Delridge Way in the past few days, you’ve seen crews staging in a big way for the repaving-and-more project that’s preceding the RapidRide H Line conversion. Here’s what happens in the coming week, SDOT says:
What to expect the week of June 22
We will work in all three zones at the same time, from north to south on Delridge Way SW. No-Parking signs will be posted on both sides of the street in each phase of work to shift traffic around the work zones.
Work by zone
Zone A (West Seattle Bridge to SW Findlay St)
Curb ramp removal at SW Charlestown St
As early as Monday, June 22 we will be removing the northern curb ramp at SW Charlestown St. This work is expected last for one day. Please follow any posted pedestrian detour routes.
Access to the parking lot at SW Charlestown St may be restrictedDemolition work from SW Charlestown St to SW Dakota St
For the next few weeks, we will be completing demolition work in the roadway and sidewalk between SW Charlestown St and SW Dakota St. Lanes will be shifted around the work zone.SW Genesee and SW Oregon streets
We will continue conducting utility and storm work. Please expect traffic to be shifted to one side of Delridge Way SW.SW Alaska St
Pipework will begin this week and last through the week of June 22Zone B (SW Findlay St to north of SW Orchard St)
SW Findlay St to SW Juneau St
We will continue installing utility pipes. Please expect traffic to be shifted to one side of Delridge Way SW.Zone C (North of SW Orchard St to White Center)
We will finish connecting catch basins throughout this zoneWork throughout the corridor
Continued potholing for utility work
In each of the three work zones, travel lanes will be reduced to one lane in each direction with restricted turns. Please follow posted traffic signs.
Upcoming work
New temporary left-turn pocket lanes at SW Orchard St will be installed later this summer to allow people driving to make left turns onto Delridge Way SW. These turn pockets will also be included when we install the final project street configuration.
See the full advisory here.
| 3 COMMENTS