Highway 99 tunneling update: First the barge, then a sinkhole

January 13, 2016 4:10 pm
|    Comments Off on Highway 99 tunneling update: First the barge, then a sinkhole
 |   Alaskan Way Viaduct | Highway 99 tunnel | West Seattle news

4:10 PM: More news today from WSDOT, the day after the Highway 99 tunneling machine had to stop while they sorted out a problem with the barge that was collecting excavation spoils. The barge problem isn’t fixed yet, but they brought in some trucks, and digging resumed. Then came a sinkhole. Here’s the WSDOT update sent this afternoon:

Seattle Tunnel Partners resumed mining Tuesday evening, using trucks to remove excavated material while they continued working to resolve an issue with a soil-removal barge. STP crews resumed excavation at 7 p.m. Tuesday.

(WSDOT graphic)
Approximately two hours later, a sinkhole developed within STP’s work zone near South Main Street, about 35 feet north of the access pit. It is located more than 100 feet south of the cutterhead’s current location, in ground that crews mined through last week. STP filled the sinkhole overnight with 250 cubic yards of concrete.

This section of the tunnel drive is protected by an underground wall built by STP before tunneling. The wall was designed to isolate ground movement and protect the nearby Alaskan Way Viaduct. A manual survey of the viaduct conducted after the sinkhole developed found no movement. WSDOT and STP will continue surveying and monitoring the ground, viaduct, utilities and other structures.

The cause of the sinkhole is still under investigation. STP is analyzing the portion of the tunnel that crews have excavated since mining resumed. There is no indication that any other locations have experienced ground loss.

STP is reviewing their daily operations as a result of this incident. Immediately they will enhance monitoring protocols by requiring crews to manually verify the amount of soil removed during excavation of each ring.

The protocols STP outlined to enhance monitoring were used in the first 1,000 feet of tunneling and WSDOT is disappointed they were not used when STP restarted tunneling in December 2015. STP has several hundred feet of mining before they reach the next planned maintenance stop. Before leaving the maintenance stop, STP’s operational protocols will undergo an additional review by an expert to assure public safety.

STP has temporarily stopped mining to prepare the muck storage pit to receive excavated material. They plan to resume tunneling this week using trucks to remove excavated material. …

Safety remains our top priority as we work to replace the seismically vulnerable Alaskan Way Viaduct. We expect STP to further investigate this incident and take the appropriate corrective action as they continue to build this important project.

ADDED 6:31 PM: We asked WSDOT’s project spokesperson Laura Newborn about the sinkhole’s size: “According to Chris Dixon, the dimensions of the sinkhole were 35 feet long, 20 feet wide and 15 feet deep.”

No Replies to "Highway 99 tunneling update: First the barge, then a sinkhole"

    Sorry, comment time is over.