Followup: Big pour at big dig by Lowman Beach starts Friday

December 3, 2014 4:33 pm
|    Comments Off on Followup: Big pour at big dig by Lowman Beach starts Friday
 |   Environment | West Seattle news

Since the big 3-day concrete pour at the excavation for the Murray Combined Sewer Overflow Control Project didn’t happen before the Thanksgiving holiday after all, we checked with the county today to ask about an official start date. It was just set today, according to Doug Marsano:

The first concrete pour is scheduled for this Friday, December 5. The last 2 pours are scheduled to occur next week on Tuesday, December 9 and Wednesday, December 10.

Work will occur from 7 a.m. – 6 p.m. on each day. The entire area will be extremely busy on those three days, and additional flaggers will be on site to ease congestion around the site. Local and emergency access on Beach Drive S.W. will be maintained throughout.

Starting tomorrow, Thursday December 4, no parking will be available on weekdays along Lincoln Park Way SW between Murray Avenue SW and Beach Drive SW, or on Beach Drive SW between the work site and Lowman Beach Park until the pour is complete.

As reported here two weeks ago, that pour will involve 20 trucks an hour.