More Seattle City Light modernization work is on the way between The Junction and Morgan Junction. If this affects you, SCL says, you should have received a flyer. In case you didn’t – or otherwise missed it – we’re sharing the news too:
Seattle City Light is continuing to make electrical improvements in portions of West Seattle by increasing capacity from 4 kV to 26kV. The attached flyer was mailed recently and explained the details to affected customers. …
· What is the work? Conversion of service from 4 to 26kV will improve the electrical capacity in a neighborhood north of Morgan Junction. This modernization has been ongoing in different portions of West Seattle since 2008. The work involves replacing old poles with new ones and adding new cross arms, insulators, transformers and wires.
· What is the schedule? Beginning of November for approximately two months. See flyer for details.
· What are the impacts? Affected customers will experience a maximum of three outages during this work. Crews will place a door hanger or make personal contact 48-72 hours in advance of outages. The notification will specify the date, time and duration of the outage.
· Point of Contact? Michael Gabrielson, Electrical Service Representative, at 206-386-4245 or michael.gabrielson@seattle.gov , or visit seattle.gov/light/aboutus/construction
This is separate from the other West Seattle work that City Light announced earlier this month, cable maintenance via silicon injection in Fauntlee Hills and Sunrise Heights.