By Tracy Record
West Seattle Blog editor
Four updates today on the planned charter middle/high school at what’s now the Freedom Church/Jesus Center on the southwest corner of 35th/Roxbury, almost six months after we discovered the proposal:
DEAL CLOSED: The nonprofit that’s developing the school for California-based charter operator Summit Public Schools, Washington Charter School Development, has closed the deal to buy the property. King County records show the purchase price was $4,750,000, almost $2 million more than the site’s 2008 sale price.
TWO-PHASE SITE DEVELOPMENT: Once we found the records of the purchase, we started checking on the status of the plan to remodel and add onto the former supermarket building at the site, and discovered a change in the plan: It’s now going to be developed in two phases, confirms a spokesperson for WCSD, which is affiliated with Los Angeles-based Pacific Charter School Development. First, they’ll remodel the existing building, and they’ve applied for a building permit to do that. The proposed additions (shown here a month ago) would be in a second phase. The school itself would be phased in anyway – Summit says it would start with 6th and 9th grades and add middle/high grades each year until fully enrolled as 6th through 12th.
CHURCH STAYING TFN: Summit Public Schools is still more than a year away from its proposed opening (and awaiting state approval, required because charter schools operate with public funding). So in the meantime, WCSD says, Freedom Church/Jesus Center is “renting back the building for the near future to allow the Church to continue providing its outstanding and award-winning community service in West Seattle while plans for the school are being finalized.” In addition to the church, the center also works with a variety of community programs and partners, including the Seattle Youth Violence Prevention Initiative.
PUBLIC FORUM NEXT MONTH: According to the calendar for the Washington Charter School Commission – which will have to approve Summit’s application (linked here) before it can open the school – a public forum is planned at the site as part of the process (as mentioned in our previous update), 6 pm July 21st.