FOLLOWUP: City says Morgan Junction Park expansion is $7.5 million project, with $4.8 million already spent

(WSB photo, park addition site, last month)

By Tracy Record
West Seattle Blog editor

Last month, as reported here, the Morgan Community Association and Morgan Junction All-Wheels Association sent a long list of questions to Seattle Parks. The questions were largely generated by an unsatisfying briefing at the quarterly MoCA meeting regarding the long-in-the-works Morgan Junction Park Addition project.

Backstory: After community sentiment swelled for adding a skatable “all-wheels” feature to the plan – aka a skatedot – the city said that could be done, and MJAWA formed to do what its community volunteers could to help make it happen. Then recently the city said it didn’t have money after all to include that in the project, so MJAWA would have to lead community fundraising to pay for it – and at a much higher price than skating infrastructure experts had said it would take. All this happened against the backdrop of interdepartmental trouble over finishing the process of cleaning up the site, which currently is pretty much a giant fenced-off hole.

So the questions had to do with clarity about the budget and the project status. The Morgan Community Association received a document today with at least some of the replies. Here’s the document; following are a few key points:

*Project budget: $7,560,000, including acquisition costs more than a decade ago. We were told at the time that the purchase price was just under $1.9 million, but the Parks document lists “acquisiion cost” as $2.7 million, without a breakdown.

*Spent so far: $5.7 million, including the aforementioned acquisition costs and $1.6 million described as “construction” though nothing’s been built at the site (Parks says cleanup work done so far is part of this).

*Remaining money: $1.8 million

*What they expect to need: The entire $1.8 million (more than half of that for the actual park construction – not including a skateable feature – $900,000 construction contract, $300,000 expenses such as sales tax and “escalation”)

But the most significant numbers differential is between what renowned skatepark builders at Grindline, who have worked with MJAWA on a design, believe it would cost, and what Parks says it would cost. In the new document, Parks says:

The cost estimate provided by Grindline varies from the cost estimate provided by SPR for the following reasons:

Grindline’s estimate EXCLUDES a number of critical items: Design/Design review support (geotech/structural/civil/larch, etc.), SPR Labor (inspections and PM), Contractor labor, escalation (estimate is from 2024), survey, demo/disposal, earthwork, drainage, supporting sitework outside the feature (concrete/plantings, etc.) contractor mobilization/markup, sales tax, and design/construction contingency. It also excludes the cost to address improvements associated with the skatedot but not within the footprint.

SPR numbers include estimates for these items at a schematic level and are comprehensive of the total project cost. These costs will be refined as we move forward and the design becomes more detailed.
Skatedot Cost Estimate Overview:
Grindline’s 2024 estimate: $160,000 (w/o tax)
Design team’s 2024 professional cost estimator for skatedot materials and labor
only: $300,000 (w/o tax)
SPR’s escalated hard cost estimate (incl tax, contingency, and anticipated
supporting site work): $700,000
Additional Design fees anticipated: $150,000
Total cost:~$850,000

Once again, this estimate will likely be reduced as the project moves through the design process and uncertainties are resolved. SPR is committed to working with MJAWA to refine the design, hone in on cost, and try to find a path forward that works best for the park and community.

More followups to come, but for those interested in the ongoing saga, we published the questions so wanted you to have the chance to read the first round of answers. (The document also has some information on what’s next and when, saying most of the project site should be ready for hydroseeding next month – once the hole is filled – to grow grass that would enable temporarily reopening the site to public use.)

39 Replies to "FOLLOWUP: City says Morgan Junction Park expansion is $7.5 million project, with $4.8 million already spent"

  • Su August 2, 2025 (3:18 am)

    That’s a lot of money, a lot of time, for a hole on the ground so far. Am I missing something? We could use a break down on the expense and blueprint.

  • Eye roll August 2, 2025 (6:54 am)

    The hydro seeding should grow really well considering how much BS the department is spewing.  Trust the parks, not the company that has built hundreds of skateparks around the world, to know how much it costs to do their job.  Makes perfect sense. 

    • k August 2, 2025 (7:19 pm)

      Parks did a good job of listing exclusions in Grindline’s estimate that definitely should have been included and definitely add up to a lot of money.  Parks isn’t questioning how to build the skatepark, just pointing out that their estimate was very, very, shockingly incomplete.  

  • Tax Payer August 2, 2025 (7:33 am)

    Now google what $7.5M gets you in the private sector by looking at homes. You’ll start to see how corrupt government is. And this isn’t an uninformed rant. I’m the Controller for a $700M company that does work in both sectors. 

    • Kimberly August 3, 2025 (12:45 am)

      Holy hell, I believe it and it makes me sick. Think of the millions they have spent so far to help the homeless here but yet what have they actually done??? 

      • Neighbor August 4, 2025 (5:52 am)

        Have you looked?  The city has helped thousands of people get off the streets.

  • Little One August 2, 2025 (8:56 am)

    This is a fairly high-level budget breakdown. Parks should provide more details when it lists cost escalation and additional costs. I’d also be interested in seeing the design and contractor invoices.

    Some questions for Parks:

    – The budget lists $900k for contract award + $350k for tax, contingency, escalation. The narrative says $700k for the hard estimate WITH tax, contingency, escalation plus $150k for additional design.

    – How did they go from their own $300k (w/o tax) 2024 estimate to $700k (w/ tax, contingency, escalation)? That is 130% additional that can’t all be tax, contingency, escalation.

    – $643k for “planning, design, project management, and administrative costs” for remaining work. That is over 50% of the listed remaining Construction Expenses.

    – Overall $1.2 Million for Planning, Design, and the above $643k. That is Overall $1.2 Million planning/design/admin costs for $3.6 Million of construction. That is overall 33% costs for what I assume is the City’s effort and any consultant effort.

    This project wasn’t much on my radar besides driving past. Seeing this, it raises red flags for what looks like a straightforward cleanup (even with the shoring) and a skate park. Good grief. 

  • Mellow Kitty August 2, 2025 (9:23 am)

    That photo shows how well 4.8 million of our tax dollars have been spent. If this isn’t a clear example of irresponsible money management, I don’t know what is. We have a 4.8 million dollar plot of dirt and not enough money to do anything with it. No. New. Taxes. 

  • Jessica August 2, 2025 (9:24 am)

    I think my teen will age out of skating before this is done, but I’m excited for the future kids!

    • CarDriver August 2, 2025 (10:55 am)

      Don’t you mean the future great grandkids-maybe if they’re lucky??

    • Tony August 3, 2025 (10:19 am)

      Weirdly at nearly 58 I haven’t “aged out” of skateboarding yet. 

  • Frog August 2, 2025 (9:29 am)

    Let’s just hope they don’t add a toilet to the design.  That would raise the cost to $32 million.

  • Justin August 2, 2025 (9:51 am)

    By endlessly drawing out the “planning and design” phases of these landbanked capital projects, Parks is able to keep their staff employed while never making meaningful progress toward construction. Perhaps that’s the real intent of these “projects”.

    • Justin August 2, 2025 (12:22 pm)

      It seems like SPR is also artificially inflating the cost of the skate park element so that they can justify dropping it from the project scope – presumably because they never wanted to include it in the first place.

  • Patrick August 2, 2025 (10:31 am)

    So when is this project going to be completed? It looks like nothing has changed in over a year or do.

  • Frank August 2, 2025 (11:00 am)

    Should we call it fraud or lying when Parks retroactively declares the acquisition cost $800,000 more than the previous number? King county Parks is just as bad: In the “Parks” levy they are requesting increased taxes for giving tens of millions to the Aquarium and Zoo. Is there a revolving door there or straight up corruption? 

  • Mr SeaVue August 2, 2025 (11:06 am)

    The Parks team that was working on this a couple years ago seemed like they had their heads on straight, what has happened? It smells…like rookie mistakes or an underhanded attempt to make the community supported / parks approved design change go away with inflated numbers. Can we get a little attention on this from our senior leaders at Parks, Mr. Harrel, Mr. Saka or investigative reporters please? The patience from the Morgan community is way past thin…make this a priority, put a parks team on it that can rebuild trust and get it delivered as scoped in the outreach documents provided to the community last year.  Stop rescoping/redesigning each time a new cost estimate shows up…get political support within the higher levels of the city to increase the priority of this project to get the funds needed to complete this.  This just feeds the narrative that the southern neighborhoods of Seattle are underserved. The community has worked in good faith with parks and with a world class designer for a part of the site that is already developed, so the need for all the additional design and site work doesn’t make any sense. Starting over with a fresh design when one has been prepared and handed to parks on a platter seems like a  complete waste of taxpayer money, private sector expertise,  and community goodwill. We know mistakes happen and things happening under the soil bring surprises. We need to accept that and be glad this old dry cleaning site illegally polluting our groundwater has been cleaned up but Parks needs to absorb these costs and and find a way to get this done. Get parks’ A-team to rebaseline this, based on real world input from the experts that are already working with the city, and rally our electeds for the funds to push this to completion ASAP. 

    • Justin August 2, 2025 (12:23 pm)

      I don’t get the sense that Parks has an “A Team”

  • flimflam August 2, 2025 (11:47 am)

    And to think the city destroyed the skate dot built DIY by skaters that WAS ALREADY THERE in a fit of “they aren’t allowed to do that!”. Money well spent?

  • Dysfunction August 2, 2025 (11:53 am)

    Another example of why government has higher inflation than the private sector. And also an example of Parks really just being a jobs program. A bloated project to begin with, not much done in a decade, and astronomical inflation in this small park. It isn’t just “greedy corporations” who have made Seattle one of the most expensive cities in the country. The government and their bloated departments are. Who is the bigger fool, the fool or the fool that supports them? In this case, Seattle Parks and the voter who complains about it and then votes for tax increases for them. 

  • Chris August 2, 2025 (2:38 pm)

    Seattle Parks is a cabal of ineptitude. Absolutely and utterly incompetent. 

  • Come ON Seattle Parks!! August 2, 2025 (2:52 pm)

    We live nearby and have been eagerly awaiting this park for SOOO long. 1) the city knew they were purchasing a property with a dry cleaner so should have anticipated the time and dollars.2) am I crazy, or didn’t we already have a park plan that included multiple rounds of input? I recall a play structure and other activating elements to keep the space lively and engaging (not just open space)3. the community energy for a skate dot was incredible, seeing the city quash that was shameful. That said, I don’t feel like the skate addition is worth the add if it is going to add time/budget to getting a park in place. 4. Morgan Junction is in the process of being further up zoned. The fact that the closest play space for children in this neighborhood is 20-30 minute walk away just doesn’t work for the lively urban center the city says it’s trying to develop for its densely populated hubs.5. What can the community do to get this process moving again? The Lincoln Park playground has been condemned, torn down and rebuilt in the time that we’ve been waiting. (And that project took forever, too). Other parks in WS seem to be moving forward, too. This project has been a blight on my neighborhood for too long. And now this expansion is likely just going to be more grass for bad behavior to happen on. Maybe I wish we had the dodgy little market and dry cleaner back.

  • wetone August 2, 2025 (3:03 pm)

    Sounds like a Sound Transit run project……..all to common these days with Seattle and Washington st government. People seem not to care about accountability today. That’s why I vote no for most all levy’s lately. Show me some results and accountability…..one of the many reasons living cost, housing and rents continue to rise in Seattle.

  • Kyle August 2, 2025 (3:56 pm)

    Good grief, someone check Parks into a Money Management course.

  • Admiral-2009 August 2, 2025 (5:46 pm)

    Why is the Fairmont Park play structure fenced off?  

  • Admiral-2009 August 2, 2025 (6:52 pm)

    The softball project is scheduled for construction Spring 2026, the fencing off of the essentially brand new play structure, 2022, has no apparent reason.

    • WSB August 2, 2025 (7:31 pm)

      That’s the only listed project at the playground/playfield. But maybe it was something urgent. I’ll of course ask Parks first thing Monday …

  • M August 2, 2025 (7:10 pm)

    This is the entire reasons I’m a republican. 

  • Nitro August 2, 2025 (8:02 pm)

    For all of the handwringing and wailing about the lack of affordable housing, the city should take that parcel and put a high rise low income apartment building on the site. It is right on the rapid transit line, grocery and amenities within walking distance. They could get a lot of units in that space of affordable housing. 

    • WSB August 2, 2025 (11:41 pm)

      It’s not zoned for “high rise.” Not even midrise. Up to five stories. But it was originally on the market as a potential development site.

      • wetone August 3, 2025 (10:05 am)

        Interesting that this property was not up zoned. When you look at what mayor Harrell and city council are allowing to happen to most most all city neighborhoods starting this fall with their new changes of residential zoning…… People really need to pay attention as your neighborhood will be a thing of the past.  With number of allowed housing units, height limits and setbacks of projects…If you have nice yard, garden or enjoy sunlight get ready for life changing build projects around you ;( We have 2 duplexes going on 6000 soft lot near us that will block sunlight to our beautiful garden, wildlife area as height limits have been raised also. If you have solar panels good luck…..  Since project  has 4 units the set back from sidewalk is only 10’ and all other houses in neighborhood have 25’-50’.  This will drive property and tax values higher as investors/builders can pay more than most everyone else…..https://www.seattle.gov/opcd/one-seattle-planhttps://dailyplanit.seattle.gov/one-seattle-plan-updates/https://www.theurbanist.org/2025/05/27/seattle-just-rezoned-the-entire-city/

        • WSB August 3, 2025 (2:20 pm)

          Not to say it might NOT be upzoned when the comp plan is passed (hasn’t happened yet, what did happen is the upzoning mandated by the Legislature, four units OK on every ex-SF lot, previously the city had already OK’d three units anyway, we have one of those on our block replacing a cottage on a 4200-sf lot), but its CURRENT zoning remains to 55′. No time to go look it up on the proposed maps right now – TR

      • DL August 6, 2025 (2:57 pm)

        Do you know what the plan is for the empty one story bank building that is on the corner there, next to the round apartment building? It had a for lease sign forever and now there is no sign but no one seems to be moving in either. 

  • Alki resident August 2, 2025 (11:13 pm)

    This is an atrocity. The kids that wanted this so badly and compassionately are likely grown by now and to think how much money was wasted and it literally looks the same is pure insanity. As much as I want to say I can’t believe it, I believe it. Money comes from trees and we just blow through it because why not. How can kids ever trust adults? Hey kids, learn to vote when you’re 18. 

  • Grilled Cheese August 3, 2025 (10:55 am)

    As an old school skater this is insane to read. I would drive by this spot all the time. It was just flat concrete. The local kids and parents built some small ramps and rails that cost probably less than $50 to make. Why couldn’t the city just build a small skate-able terrain park. At max that would cost 200-300k to build. This city planning is the worst. I want to see the receipts. 

    • Little One August 3, 2025 (10:49 pm)

      The DIY skatepark was cool. Loved the spirit of it and to see that plot being used. The site cleanup happening before a permanent setup makes sense though.  It’s removal of contamination that’s better for the long term.  The projected cost even post-cleanup is a head scratcher though.

  • CabanaMom August 3, 2025 (7:46 pm)

    Part of this site was the previous home of a dry cleaner.  I’m sure some of the cost so far was for clean-up of the site.  If contamination was found, they’d have to remove soil and replace.  That will be safer in the long run…but, I agree…it’s taking far too long.  

Sorry, comment time is over.