WSDOT says #Realign99 work is going well so far

On this third day of Highway 99-less-ness, the #Realign99 work itself is going well, according to WSDOT‘s project deputy administrator Dave Sowers. That’s what he told reporters on a late-morning conference call. One bit of the ramp-building/tunnel-connecting work is even a bit ahead of schedule, Sowers said. But he also said there’s zero chance the tunnel will open early – they’re sticking to their plan for a February 2-3 celebration weekend, and then (assuming all goes well) the tunnel opening in time for the Monday, February 4th, morning commute. We’re on our way now to a Metro/Water Taxi-specific briefing in SODO; more to come.