This P-I story about impending pole-less-ness in new fire stations — including Station 37 on 35th — got us wondering how that project and another one in West Seattle are going. We found this page on the Fire Department website with monthly reports on the fire-station projects citywide; though the newest “status report” is filed as “March 2008,” it’s dated just yesterday. For Station 37, to be built at a new site at 35th/Holden (while the old one, a city landmark, will eventually be sold), the architects are “continu(ing) on construction documents.” For Station 32 in The Junction, the report says its architects (different firm) are continuing on pre-design, and “three alternative site layouts have been prepared for comment.” Another document linked from that same city page says construction on FS 32 is scheduled to start in November ’09, while 37 is scheduled to start this August.