(WSB photo: Looking east on SW Andover late this afternoon)
We reported Monday on the removal of dozens of eco-blocks that had been placed along SW Andover and 28th SW after the city swept the longrunning RV encampment there in June. This afternoon, we finally have the full SDOT explanation of what happened and what’s planned for the area:
The eco-blocks were removed by the business that placed them. Following protocol, SDOT sent a warning notice after the concrete blocks were placed due to the lack of an approved street permit. The correspondence led to a productive conversation in which the business took responsibility for setting them and agreed to remove the eco-blocks at their own expense. During discussions, we shared plans for paving the street and discussed how the curb space and right of way currently work for businesses in the area.
New pavement being added on the north side of SW Andover Street creates space for a westbound protected bike lane, the option to leverage the paving project, and fill a gap in our bicycle network. This concept resonated with those with whom we spoke. Crews are also making drainage and landscaping improvements, which is why you noticed dirt removal. The paving of SW Andover St between 26th Ave SW and 28th Ave SW is currently scheduled for August 8-11. The paving repairs damage that may have occurred due to increased traffic during the West Seattle Bridge closure.
The bike lanes will be on both sides of SW Andover St, between 26th Ave SW and 28th Ave SW, and bike enhancements could be potentially added to SW Yancy St. The design is at about 50%, and we expect installation to be this fall. There will be no impacts to travel lanes. However, some parking and loading zones will be impacted and removed. The Bike Master Plan recommends a Neighborhood Greenway treatment. Due to the industrial nature of the area and for the comfort and enhanced safety of those biking, we are installing a protected bike lane (PBL). The Levy to Move Seattle is funding the bike lane design.
SDOT says the paving will be complete this week; the schedule for building the bike lane is not yet finalized.
| 30 COMMENTS