6:20 PM: As of 6 pm, midway through the two-hour SDOT open house for the Fauntleroy Way SW Boulevard project, about 45 people had dropped by. You still have until 7 pm to go to the Senior Center of West Seattle and get a closer look at the newest renderings for how this project would change Fauntleroy Way between SW Alaska and 35th SW (they’re also now available on the official webpage), with project manager Thérèse Casper and others standing by to answer your questions, as well as several ways to comment (from sticky notes to computer terminals).
The project is on its way to 60 percent design; if the $500,000 that’s in the mayor’s budget for the remaining 40 percent is approved, that will proceed, and then the city has to figure out how to pay to build the project’s features.
7:02 PM: Here are the renderings that were up on boards around the room at the meeting:
This is the official updated project info-sheet:
Something to say? Say it sooner rather than later – here’s one way to do that. Casper says they’re continuing to meet with local businesses and organizations and have already met with some businesses multiple times, to go over points of concern.
| 5 COMMENTS