Seattle City Light Brace Point project meeting

When:
August 4, 2021 @ 12:00 pm
2021-08-04T12:00:00-07:00
2021-08-04T12:15:00-07:00
Where:
Online
Cost:
Free

Underground electrical cables were originally installed in parts of the Endolyne/Brace Point area in 1971. In 2011, a Seattle City Light contractor tested and where possible, injected the cables with silicone to extend their life. However, several cable segments could not be injected and must be replaced. City Light has hired a contractor to replace the aging electrical infrastructure in the Brace Point area with new conduits, cables, vaults and streetlights. This work is tentatively scheduled to start in August 2021.
Customers can learn more about this project by attending our virtual community meeting on Wednesday, August 4, 2021, from noon to 1 p.m.
Register for this meeting by visiting bit.ly/brace-point.