Search Result for : speed cushions

Speed-hump building has begun, and other updates @ HPAC’s second meeting of spring

(WSB photo, SW Barton west of 9th SW)

By Tracy Record
West Seattle Blog editor

New speed humps are popping up all over Highland Park, South Delridge, and Riverview. SDOT is building up to six a day, and sent reps to HPAC‘s monthly meeting to talk about Home Zone progress and other Reconnect West Seattle projects meant to tackle bridge-detour cut-through traffic.

SDOT’s Sara Zora and David Burgesser began by announcing the RWS project dashboard – centered on a map – has been updated.

A quarterly report is now out, too – here are the key points:

Read More

29 new speed humps on the way to Arbor Heights

That map shows where SDOT is planning speed humps to slow drivers near Arbor Heights Elementary and Westside School (WSB sponsor). We contacted SDOT for more details after a postcard landed in Arbor Heights mailboxes and reader Andrew forwarded it as an FYI. The map (here’s a PDF version) shows 29 speed humps planned for streets that already have 20 mph school-zone signage, says SDOT spokesperson Ethan Bergerson. He adds that this is part of the Safe Routes to School program. Construction isn’t scheduled yet, he says, but won’t happen any earlier than May; the mailer was meant to be an early warning of sorts.

ADDED WEDNESDAY: SDOT explains the color-coding as – red for speed humps, blue for speed cushions. Here’s an explanation of how they differ.

West Seattle traffic: 48th SW speed bumps close to installation

12:25 PM: The 48th Avenue SW straightaway through Seaview toward Genesee is about to get bumpier – on purpose. SDOT confirms that the four sets of speed bumps – one per block between SW Graham and SW Brandon – are scheduled to be installed today, in the places where the road was recently painted (as shown in our Tuesday photo above) to show their planned placement. According to SDOT’s Rick Sheridan, “There will be a total of 16 cushions installed – four from curb to curb on each of the four blocks. The speed cushions are designed to calm traffic while still allowing buses and emergency vehicles to maneuver without difficulty. We plan to carry out the installation today, however, the department is still awaiting the delivery of materials needed for the work.”

5:21 PM UPDATE: Went back to 48th SW to check:

We found an SDOT crew working on part of the road, but it looked like repairs, not installation. Maybe tomorrow.

New Southwest Precinct commander, neighborhood updates @ District 1 Community Network

The District 1 Community Network‘s monthly online meeting last night included many quick updates as well as a brief chance to meet the Southwest Precinct‘s new commander:

CAPT. MARTIN RIVERA: SPD’s new Southwest Precinct commander is on the job (as reported here) and sat in on last night’s D1CN meeting to start getting acquainted with community groups. Capt. Rivera explained that he was previously the night-duty captain, which means responding to any major nighttime incident in the city. Before then, he worked at the West Precinct – which includes downtown – and served in a variety of other roles in his 22 years with SPD. He was promoted to captain last year, according to his bio on the precinct website (which is the source of the photo at right).

The D1CN meeting, facilitated this month by Marty Westerman of the West Seattle Transportation Coalition and Fauntleroy Community Association, also featured an update from the gondola advocates of West Seattle SkyLink and a variety of quick neighborhood notes:

Read More

What SDOT heard at HPAC discussion. of Delridge/Highland Park ‘Stay Healthy Streets’ future, and your chance to comment today

By Tracy Record
West Seattle Blog editor

SDOT has proposed a permanent route for the Delridge/Highland Park “Stay Healthy Streets,” with some current blocks to be dropped – but keeping the stretch that’s been the source of the loudest community concerns. They’re nonetheless asking for opinions, and hosting an outdoor “open house” today on 11th SW by Highland Park Elementary, 2-4 pm. In advance of that, SDOT reps were at Wednesday night’s HPAC meeting to talk about the Stay Healthy Streets as well as traffic-mitigation/calming events elsewhere.

STAY HEALTHY STREETS: first, a little backstory. These streets are closed to through-traffic, open to drivers who live, work, study, or otherwise have business on them, and open to people walking/running/riding/rolling in the street. The city launched the SHS concept early in the pandemic as a way to get around with more social distancing, but has expanded the mission beyond the pandemic, and is now making many of them permanent. The Delridge-Highland Park SHS network (designated in May of last year) would be the second in the city (after Greenwood) to be made permanent, SDOT’s Madison Linkenmeyer told HPAC.

She recapped what they’ve heard from the community:

Read More

WEST SEATTLE TRANSPORTATION COALITION: Bridge catchup, light-rail lookahead, 16th SW slowdown hopes

By Tracy Record
West Seattle Blog editor

This month’s West Seattle Transportation Coalition meeting provided an opportunity to catch up on some of our area’s biggest projects.

WEST SEATTLE BRIDGE & VICINITY: Two guests from SDOT were there. Danielle Friedman recapped key points from the Community Task Force‘s most-recent meeting (WSB coverage here) – repair work starting this fall (she said “October or November”), Reconnect West Seattle projects continuing including the West Marginal/Highland Park Way intersection and temporary signal at Duwamish Longhouse “starting any minute now” (but that too will be primarily weekend work, she said).

Read More

FOLLOWUP: See what’s in the final ‘Home Zone’ plans for Highland Park, Riverview, South Delridge

By Tracy Record
West Seattle Blog editor

More than 70 locations for speed humps/cushions are part of the final plans for “Home Zone” traffic-calming in Highland Park, Riverview, and South Delridge neighborhoods besieged by detouring drivers since the West Seattle Bridge closed a year ago.

The plans were presented last night – along with side notes about a new stretch of greenway and the bridge itself – at an online meeting led by SDOT and Department of Neighborhoods reps.

THE PLANS: First, the definition of Home Zone:

SDOT did traffic counts at more than 39 locations and took three walking tours while coming up with the draft plan presented in January. They also offered a survey that brought 542 responses. 59 percent of respondents felt the draft plan was missing something that would make them feel safer – 300 suggestions came in. “About 30 percent were things we can accommodate in the Home Zone plan or look into further,” said SDOT’s David Burgesser. The rest were too general, not feasible, too expensive, or put aside for future consideration.

SOUTH AREA HOME ZONE PLAN

Read More

FOLLOWUP: SDOT’s options for future of Alki Point ‘Keep Moving Street’

(WSB photo, Beach Drive “Keep Moving Street” in May)

Also from West Seattle/South Park City Councilmember Lisa Herbold‘s weekly update, new information on options SDOT is considering for the future of what’s currently a “Keep Moving Street” on both sides of Alki Point. Three weeks ago, SDOT announced those sections of Beach Drive and Alki Avenue would keep their no-through-traffic status at least until King County moved to Stage 3 of COVID-19 recovery. Nearby residents have been collecting petition signatures in support of making it permanent, as Herbold notes in her update, saying she “support(s) the continued efforts of constituents advocating for a permanent Stay Healthy Street.” She says she contacted SDOT with questions about the status and in reply, the department told her five options are under consideration:

1. Return to previous street operation

2. Convert to a neighborhood greenway, changes would include:
-Stop signs at intersecting streets will be added where they currently operate as neighborhood yield intersections (64th Ave SW, Point Pl SW, 64th Pl SW, 64th Ave SW)
-Additional traffic calming so that spacing of speed humps and raised crosswalks is approximately every 300 feet
-Approximately 3-4 speed humps or speed cushions would be added.
-Connectivity to the citywide bicycle network would be enhanced through the addition of sharrow pavement markings and wayfinding signs.

3. Upgrade to a permanent Stay Healthy Street, changes would include:
-All of the neighborhood greenway enhancements listed above
-Street Closed and Stay Healthy Street signs at every intersection with durable materials

4. Upgrade neighborhood greenway with additional space for walking adjacent to beachside curb.
-All of the neighborhood greenway enhancements listed above
-Removal of parking and delineation (tuff curb and post) of additional space for walking adjacent to the existing sidewalk adjacent to the beach
-Increased space for walking would be adjacent to park beach only, not continuous where buildings are between roadway and beach.

5. Convert street to operate as one-way northbound for vehicles, providing shared walking and biking space adjacent to beachside sidewalk
-Delineation of a continuous shared walking and biking space adjacent to the existing beachside curb (8’ to 15’ wide)
-Continuous shared walking and biking space would connect from the existing Alki Trail to the end of the Alki Point Keep Moving Street.
-Adjustment of the roadway to operate as one way northbound for vehicles, preserving parking primarily adjacent to east/south curbs.

Herbold says SDOT assured her the street’s status wouldn’t change “until the community engagement process concludes and there is a final determination regarding a permanent configuration.” There’s no elaboration on exactly what the “community engagement process” entails, but the Stay Healthy/Keep Moving Streets project webpage has a contact email: StayHealthyStreets@seattle.gov.

FOLLOWUP: Highland Park traffic-calming, round 1, almost done

Even as the Reconnect West Seattle feedback process continues, Highland Park already has had some traffic-calming measures in the works. Last week, Cindy sent us a photo of a sign that’s already installed and waiting along 9th SW – though the speed bumps it mentions aren’t in place yet:

We checked with SDOT on the installation status, and they sent us the map above, saying, “We have completed installing all of the traffic calming measures everywhere except 9th Ave SW, which we are still working to schedule.” As noted on the map, the 9th SW installations are planned as “speed cushions” – here’s the difference, as explained by SDOT:

Speed humps are designed to slow traffic speeds on low volume, low speed streets. They are a solid hump across the travel lane and are installed near streetlights where they will be visible to people driving and biking.

Speed cushions are typically installed where average speeds are 5 mph higher than the speed limit. Speed cushions leave space for emergency vehicles to pass through quickly and are used on designated fire and emergency routes on residential streets.

This project also included the Highland Park Way/Holden traffic signal that was rush-installed right after the West Seattle Bridge closure, after local residents had worked for years to get safety upgrades at that intersection.

P.S. If you live/work/travel through the area, be sure to give your feedback on the neighborhood-specific list of more potential projects, before July 31st.

What SDOT told HPAC about Highland Park Area Safety Project – pending funding finalization

(SDOT slide deck from HPAC meeting – or see it here in PDF)

What SDOT now calls the Highland Park Area Safety Project was the first of two major topics at last night’s HPAC meeting. (The other, Westcrest Park Off-Leash Area, will be covered in a separate report.)

It’s meant primarily to address the long-problematic Highland Park Way/Holden intersection, but the scope has broadened, SDOT says. Thought the agency’s director Sam Zimbabwe had been announced, he wasn’t there; an SDOT delegation led by Jim Curtin and James Le handled the presentation and Q&A instead.

Bottom line, as Curtin reiterated multiple times, this is contingent on whether Mayor Jenny Durkan‘s proposal for funding – taken from the city’s so-called “Mercer Megablock” sale proceeds – is finalized by councilmembers in November. That said, they talked with the 30+ meeting attendees about where they’re at and what residents think. Read More

ROAD-WORK ALERT: 59th SW on Sunday

August 22, 2019 2:49 pm
|    Comments Off on ROAD-WORK ALERT: 59th SW on Sunday
 |   West Seattle news | West Seattle traffic alerts

We checked with SDOT after a reader question about why 59th SW is lined with “no parking” signs for this Sunday (August 25), 7 am-5 pm, between Admiral Way and Alki Avenue. The only hint on the signage was attribution to the AAC (asphalt/paving/etc.) division. Here’s what SDOT spokesperson Ethan Bergerson tells us: Crews will be out on Sunday removing the rubber speed cushions on 59th SW and replacing them with asphalt speed cushions.

Neighborhood traffic-safety talk launches West Seattle Block Watch Captains Network for Year 5

By Tracy Record
West Seattle Blog editor

Deb Greer and Karen Berge, founders of the West Seattle Block Watch Captains’ Network, launched its first meeting of 2014 by announcing proudly that WSBWCN is starting its fifth year.

They have always noted that you don’t have to be a captain, or even a Block Watch member, to attend, and in fact, about a third of the ~15 attendees said they were not – though some were getting ready to organize one. Others, meantime, identified themselves as longtime captains.

Also on hand for the meeting in the Southwest Precinct‘s meeting room: The precinct’s current top two leaders, new commander Captain Pierre Davis and Operations Lt. Ron Smith.

Capt. Davis told the group that Block Watches are the first step to “helping us catch the bad guys” and that the setup here in West Seattle is “second to none,” a “true partnership.” Lt. Smith echoed the appreciation and reiterated, “If you see something suspicious, report it.”

Centerpiece of the meeting was an appearance by Stephen Padua of SDOT, talking about the city’s Neighborhood Traffic Operations program – making clear he’s taking about neighborhood streets, not arterials. (Volume defines which streets are arterials and which are not – there’s a different process for arterials.)

Read More

TRAFFIC/TRANSIT TODAY: Wednesday on wheels, including 2 road-work updates

(Live view from the east-facing WS Bridge camera; see other cameras on the WSB Traffic page)
Above and below, a look at our two key commuter paths – the bridge and Highway 99 …

… and within West Seattle, there’s one traffic alert for today, and beyond, sent late Tuesday by SDOT:

Due to the high degree of maintenance needed by the rubberized speed cushions on SW Dawson near 18th Ave SW (map), SDOT will reconstruct these speed cushions in asphalt. The speed cushions were constructed with three other sets some time ago through a Neighborhood Street Fund grant. The community had documented relatively high speeds; 15% of the vehicles were traveling over 35 mph. Speeds slowed significantly as a result of this project.

SDOT will remove the rubber speed cushions on SW Dawson and cover the warning signs. The speed cushions will then be rebuilt in asphalt and the signs uncovered. The rubber speed cushions may be removed as early as this week. As asphalt is somewhat weather dependent, there may be some lag before the cushions are rebuilt.

And in case you missed this when we published it late Tuesday – here’s the detour map/plan for this weekend’s total shutdown of the Delridge/Henderson intersection.

West Seattle streets: One project next week; two later this spring

We had heard that a notable amount of road work was scheduled around West Seattle while (most) schools are out next week, so we checked with SDOT to see what’s on the schedule. Turns out one project is indeed on, while two others in the Morgan Junction/Gatewood area have been pushed back to a bit later this spring. Here’s the update from SDOT’s Marybeth Turner:

Next week we plan to replace two speed cushions at 59th Avenue Southwest near Alki Elementary School.

You may have heard about two upcoming pedestrian safety projects on California Avenue SW. These are now scheduled to be built late in March or early spring, depending on when our crews can fit them into their schedules and also depending on the weather.

One of the projects is at SW Othello Street and California Ave SW. We will build a curb bulb on the east side of California to shorten the crossing distance and improve visibility for pedestrians waiting to cross. A new overhead crosswalk sign with flashing beacons will also be installed.

The other project consists of building curb ramps that meet current standards at the intersection of SW Frontenac Street and California Ave SW, on the northwest, southwest and southeast corners. Also, the sidewalk will be replaced on the northwest corner.

We also had some information on the 59th SW speed humps courtesy of Councilmember Tom Rasmussen‘s office; the current rubber humps will be removed and replaced with “asphalt (ones) that are similar in profile,” according to a neighborhoodleader. You’ll see some no-parking restrictions in the area during the work.

Delridge District Council report: New chair; lots more updates

In addition to the Washington State Ferries Draft Long-Range Plan public hearing in Fauntleroy (WSB coverage here) and the last Seattle School Board meeting before the school-closure vote (WSB coverage here), we have coverage for you from one more Wednesday night event — the Delridge Neighborhoods District Council monthly meeting, which included updates on a multitude of local events and projects, as well as a leadership change, and more details on the upcoming Gathering of Neighbors – read on:Read More

The bumps near the bumpiness: 16th SW update

Thanks to several WSB’ers for e-mailing us in the past day and a half or so to point out that those speed bumps have just gone in on 16th SW north of South Seattle Community College. The ironic and head-scratch-inducing aspect of the installation, however, is that they are very close to the massively pitted stretch of 16th SW that was supposed to be repaved this year (but as we reported last month is now on hold till 2009). So what’s up with that? we were asked. We in turn relayed the question to SDOT, whose communications chief Rick Sheridan managed to track down the vacationing project engineer to retrieve this explanation:

The speed cushions installed by SDOT on 16th Avenue SW are part of a series requested and approved as a small Neighborhood Street Fund (NSF) project. After the community requested them through the NSF process, SDOT studied vehicle speeds in the area and determined that speeding could be controlled with these devices. Speed cushions will be installed on 16th Avenue SW, SW Dawson Street and 21st Avenue SW.

When the work is complete, 16th Avenue SW will have two sets to help address speeding. The first set, reported by your readers, was installed in an area that is not scheduled for repaving. The second set will be installed in an area of 16th Avenue SW that, funds permitting, will be repaved and so we are waiting until that work is accomplished.

Got questions? We do our best to get answers, so we’re always glad to get notes about sightings like this … we don’t say “thanks” often enough. Any time: editor@westseattleblog.com (or if you’re on Twitter, @westseattleblog)

WS Safety Partnership tonight: Traffic-trouble help on the way

morganportableradar.jpg

On our way to tonight’s West Seattle Community Safety Partnership meeting at the Southwest Precinct, we spotted that radar-powered speed sign along westbound Morgan, just west of 40th, where people barrel down the hill toward Fauntleroy/California (we only registered 7 mph because we had to slow down for the photo!). This was a timely sighting because most of the WSCSP meeting was about this type of solution to some of West Seattle’s traffic problems — the method the experts refer to as “traffic calming” — here’s some of what’s in store, and where:Read More

FAUNTLEROY FERRY TERMINAL: Where the planning process stands, with another advisory group meeting Tuesday

Washington State Ferries‘ planning process for the Fauntleroy terminal/dock replacement remains in the very early stages. Two of the three advisory groups for the project met last week, and another one meets tomorrow afternoon. We covered the first two meetings, which mostly reviewed the same material, then invited questions from advisory-group members. All meetings in this process continue to be held online. Here’s the slide deck, followed by highlights of what we saw/heard:

Read More

WEST SEATTLE BRIDGE: What’s next

(WSB on-the-road photo, looking toward the bridge from West Marginal Way)

By Tracy Record
West Seattle Blog editor

The next public updates on the 16-months-closed West Seattle Bridge and associated projects are expected this Thursday (August 12th) at the monthly Community Task Force meeting.

But you’re not likely to hear anything revelatory about the repair/reopening timeline. SDOT‘s bridge project director Heather Marx tells WSB a schedule update is more likely next month, as repair contractor Kraemer North America is using the “60-percent design” to work on that right now.

Some repair preparation is under way, too – an asbestos survey has been completed, and ordering of materials is getting under way, according to Marx, who was joined in our conversation by Sara Zora, who heads up the Reconnect West Seattle program.

Read More

Beach concerns, police update, Stay Healthy/Keep Moving Street advocacy, more @ Alki Community Council

With summer approaching, the Alki Community Council focused on beach concerns at its monthly meeting online tonight. Here’s what happened:

POLICE UPDATE: Representing the precinct was acting Lt. David Terry, a 20-year SPD veteran who currently leads the night shift. He started off by saying that “a lot of officers are dedicated to Alki” because it’s a priority for the precinct, which has “added extra resources” to work in the beach area. He mentioned the SPD crime-data dashboard, which you can use to track incidents in specific neighborhoods, Alki included. In the last four weeks, 3 misdemeanor assaults, 12 property crimes. West Seattle in general has seen 2 shots-fired incidents with no injuries and 1 injury shooting (16th/Roxbury) recently. One person complained that she was on hold for 20 minutes one recent night and never saw police despite street racing and other problems. Lt. Terry explained that some major incidents have taken away personnel – such as a South Seattle shooting response that required officers to be pulled from the Southwest Precinct. He said SW commander Capt. Kevin Grossman has since tried to work out a way that the local precinct won’t be totally depleted by any such future calls. Some West Seattle calls have taken every available resource too, like the aforementioned shooting. On weekends, they have extra OT crews until midnight on Alki. If something is happening now, call 911, not the non-emergency line, he stressed. The attendee said she had been told by an officer later that they weren’t supposed to interfere with street racing, and Lt. Terry said that’s not true – there is no such directive – so he’s talking to his officers to stress that they are not under orders to “stand down.” Racing calls are now “priority 1.” he said, which means mandatory dispatch – even if that means pulling someone from elsewhere in the city.

Read More

About those black-bagged signs in Arbor Heights

From the “you asked, so we asked” file – those new black-plastic-covered signs in Arbor Heights are for the upcoming speed humps/cushion installations, and we’ve found the plan is for more than originally announced. When we first reported on them after a reader tip last month, SDOT‘s map showed them within a few blocks of Arbor Heights Elementary and Westside School (WSB sponsor). But now the plan has gone behind that map – three added on SW 106th “in the long block between 39th Ave SW and 35th Ave SW” (above), and two planned for Marine View Drive (below):

SDOT says the Marine View Drive speed humps are meant “to improve safety along the [bridge] detour route as part of the Reconnect West Seattle program.” All the signs will be uncovered when the speed humps/cushions are installed soon.

Highland Park Way hill rechannelization on hold, and other news from HPAC’s discussion with SDOT

By Tracy Record
West Seattle Blog editor

The proposal to remove one downhill lane of Highland Park Way traffic and add an uphill protected bicycle lane is shelved for now.

That was the big headline from last night’s HPAC discussion with SDOT, a week and a half after that particular detail of the Highland Park Way/Holden safety project update came to light, sparking controversy.

Instead, SDOT will focus on figuring out how to expand the trail along the downhill lanes.

But first, HPAC got a West Seattle Bridge update that segued into traffic issues. SDOT’s Heather Marx recapped where things stand and what’s been done related to traffic effects – all of which we’ve reported on, but if you’re interested in a recap, check out this SDOT post from earlier this week, and our most-recent update. On the bridge itself, they’re preparing for Pier 18 work, and the new Community Task force and Technical Advisory Panel will have their first meetings the week of June 8th.

Traffic-mitigation projects will be focused on what can be done in less than a year and for less than $100,000 because that way SDOT doesn’t have to send them out to bid and can move faster. Plans, she said, will address effects on SODO, South Park, Georgetown, Highland Park, Riverview, South Delridge, Roxhill – in other words, the areas now getting barraged with detour traffic. When the draft traffic-mitigation plans are out, they’ll look for community prioritization. The timeline for the plans is approximately:

Read More

2016 LOOKBACK: West Seattle’s transportation Top Ten

The challenges of getting to, from, and around our peninsula make transportation a hot topic just about any time. So here’s our view of the top 10 transportation stories, for another 2016 lookback:

#10 – UNDER-THE-BRIDGE PROJECT WINS NEIGHBORHOOD STREET FUND

(May 2016 photo contributed by Chris, showing one traffic-choked morning at south section of the project zone)

In October, West Seattle Bike Connections found out that its proposal for the Harbor/Avalon/Manning/Spokane intersection, basically under the west end of the West Seattle Bridge, would be funded. This will help with safety and flow at an increasingly busy confluence of paths, roads, and bridge on-/off-ramps.

*************

#9 – FAUNTLEROY EXPRESSWAY CUSHIONS RE-REPLACED

(WSB photo, June 2016)

674 quake-safety cushions under the deck of the Fauntleroy Expressway (southwest end of the West Seattle Bridge) had to be re-replaced because of a design flaw. The work started in May and, despite requiring more than a few bridge closures, proceeded fairly painlessly, traffic-wise, over the ensuing two months.

*************

#8 – WASHINGTON STATE FERRIES VOWS TO FIX FAUNTLEROY-VASHON-SOUTHWORTH

fauntboard2
(WSB photo, October 2016, The Hall at Fauntleroy)

After a summer of problems that made things miserable for many trying to get to and from Vashon – and for Morgan Junction/Fauntleroy drivers/riders trying to get around the traffic – WSF launched a process to gather comments and make an action plan, including an October open house. Next step, launching a task force – including ferry users.

*************

#7 – ADMIRAL WAY RECHANNELIZATION

admiralprojectmap

A year and a half after announcing a controversial plan to rechannelize Admiral Way between The Admiral District and Alki, SDOT finalized it, announced it in summer, and restriped the road in fall.

*************

#6 – DOC MAYNARD BECOMES WEST SEATTLE’S WATER TAXI

What began with an Argosy Cruises vessel in the ’90s finally got its own brand-new vessel in 2016, as M/V Doc Maynard officially took over King County’s West Seattle to Downtown Seattle run in January (four months after its dedication).

Read More