More sidewalk, repaving, and utility work is planned this week as the RapidRide H Line corridor preparation project continues on and near Delridge Way SW. The project team lists these as key points for the week ahead:
*Curbs and sidewalks continue to be installed throughout Zones A and B
*Demolition between SW Trenton St and SW Henderson St to begin next week, work will include roadway, sidewalk, and curb ramp upgrades
*Roadway and sidewalk demolition in Zone C rescheduled to begin this week, with sidewalk and electrical utility upgrades to be completed in the coming weeks
*21st Ave SW at Delridge Way SW remains closed to local access only
*Intersection demolition and restoration at SW Holden St and SW Kenyon St continues
The full bulletin for this week’s work is here.
| 2 COMMENTS