TERMINAL 5’S FUTURE: Commissioners to vote Tuesday on sending modernization project to bid; lease vote in March

image1 (52)
(July 2016 aerial of West Seattle with Terminal 5 at left, shared by David)

It’s been almost three weeks since the long-awaited announcement of a tenant for Terminal 5, enabling the Port of Seattle to move forward with a $340 million plan to modernize T-5. Managing members of the Northwest Seaport Alliance – the port commissioners of Seattle and Tacoma – meet this Tuesday to vote on sending the project out to bid; their votes on the leases for T-5, short term and long term, were also originally set for this meeting but are now not expected until March 19th. Tuesday’s agenda has links to the documents that have been made public so far. From those documents, here’s the overview recapping what the $340 million project is intended to do:

Program Objectives
Program objectives include a terminal that is capable of handling two ultra-large class vessels, by early-2023. The improved wharf will support up to 12 cranes and provide ship-to-shore power for vessels berthed at the facility. …

Scope of Work
The Berth Modernization Project includes reconstruction of the waterside and landside crane rails, slope stabilization, berth deepening, and electrical supply/distribution upgrades, new fender system, and structural rehabilitation of the dock.

The upcoming program authorization request will cover construction of the Berth Modernization Project, tenant reimbursable stormwater treatment construction, and design and permitting of the remaining Uplands Improvement Project elements.

Schedule
The Berth Modernization Project construction documents are ready to advertise, allowing work to begin as early as June 2019. Completion of the project would be phased to allow operations to begin in the north berth (Phase 1) while construction of the south berth is underway (Phase 2).

The north berth is where Matson would move on an interim basis, relocating from Terminal 30, as announced when the T-5 plan was revealed earlier this month.

Meantime, if you are wondering exactly where the $340 million is coming from, we asked port spokesperson Peter McGraw. Since this is an NWSA project, Seattle and Tacoma will basically split the cost. He adds:

Port of Seattle will be using a combination of tax levy cash, currently in the Harbor Development Fund that was set aside for this purpose, and general obligation bonds.

The Port of Tacoma anticipates using existing cash reserves generated through operations and previous borrowing. No additional Port of Tacoma debt will be required to fund this program.

There will also be investments from the proposed terminal operator.

That’s SSA, which is expected to invest up to $140 million in the T-5 first phase ($50 million in cranes, $50 million in “backland paving/improvements,” $35-$40 million in yard equipment).

The aforementioned levy is a countywide tax from which the port gets some of its money and has long been collecting below its authorization level. This document includes an explanation of this year’s levy increase:

… median household property tax payment to the Port would increase by $1.39, going from $68.80 per year in 2018 to $70.20 per year in 2019. In 2018, of the $5.6 billion that King County collected in property taxes, just 1.3 percent went to the Port of Seattle. The property tax levy made up less than five percent of the Port’s cash revenue in 2018.

McGraw says, “The Port has included the T-5 modernization program into its tax levy uses for the past few years before the levy increase, set aside in the Harbor Development Fund. Although T-5 is part of our waterfront re-visioning, the bulk of the increase is going toward … other waterfront projects.”

Meantime, the next three weeks before the T-5 lease vote on March 19th, McGraw says, will be used to “complete due diligence on the leases, which are decades-long commitments involving many entities, including local companies and international cargo carriers.”

Tuesday’s meeting starts at 9 am at the Conference Center on the south side of Sea-Tac Airport, and will include a public-comment period. If you have a comment on the T-5 plan, you can also contact the NWSA via e-mail.

P.S. Tuesday’s agenda also includes more on the future of Terminal 46, part of which the Port of Seattle is proposing using as an added cruise terminal. The groundwork is being laid by an agreement between the NWSA and the port that says 29 acres at the north end of T-46 would be used as a cruise facility starting in 2022. $200 million – half – its cost is envisioned as Port-funded, the other half by its prospective tenant.

10 Replies to "TERMINAL 5'S FUTURE: Commissioners to vote Tuesday on sending modernization project to bid; lease vote in March"

  • Question Authority February 25, 2019 (5:46 am)

    What’s to gain from all this “improvement?”More taxes, more truck traffic (regardless of improved emissions) more delays on surface streets and ocean creature sadness.

  • Victoria February 25, 2019 (8:30 am)

    I am curious how the Port plans to address the following significant concern from their own study:

    To: Steven Gray, Moffatt & Nichol (M&N) From: Aaron Patterson
    (M&N)

    Date: April 20, 2016 Subject: Terminal 5 Sea Level Rise Considerations

    Project: Terminal 5 Cargo Wharf Rehabilitation, Berth Deepening and
    Improvements

    Significant Unavoidable Adverse Impacts

    Under all alternatives the existing elevation of the wharf deck will
    not be increased. As sea levels rise, increased tidal flux and wave action will
    result in waves overtopping the wharf during storm events at higher tide
    cycles.  Although rebuilding of the outer
    wharf deck under Alternative 2 and Alternative 3 would allow for the elevation
    of the outer portion to be raised to account for higher tidal elevations, the
    inner portion of the terminal would remain at the existing elevation and would
    result in grade changes that are not suitable for containerized port
    facilities.

  • Michael Taylor-Judd February 25, 2019 (11:36 am)

    We’ll be discussing transportation impacts with the Port at this Thursday’s meeting of the West Seattle Transportation Coalition at High Point Neighborhood House beginning at 6:30pm.

  • Victoria February 25, 2019 (5:00 pm)

    DSA – Here is additional information from this memorandum to answer your question (hopefully):  

    1.0 INTRODUCTION Moffatt & Nichol (M&N) has been
    retained by the Port of Seattle (Port) to provide design support services,
    including support for the State Environmental Policy Act (SEPA) review for the
    Terminal 5 (T5) Cargo Wharf Rehabilitation, Berth Deepening and Improvements
    Project (the Project). Part of this effort includes assessing the potential for
    project-related short-term and long-term impacts due to rising sea levels in
    the Puget Sound.  This memorandum describes
    existing sea levels in the study area, observed sea level rise during the 20th
    Century, projected sea level rise during the 21st Century, and what potential
    changes to the Project alternatives might occur. Measures to avoid, minimize,
    or compensate for potential adverse effects are identified. Information is
    provided in a format that can be incorporated into the Project’s in-development
    Environmental Impact Statement (EIS) as a separate chapter or as part of other
    existing EIS sections. 

  • anonyme February 27, 2019 (8:03 am)

    To date, it appears that all data indicating negative environmental impact has gone ignored.  The Port was unwilling to implement a single requirement, such as mandated shore power.  The dredging alone will decimate marine life in a broad area.  One of the big players in this, himself a whale scientist, admits that the impact on our orca population is up for speculation. Follow the money: who gets rich from this expansion?  Who (or what) suffers?  What are the overall gains to most Seattleites for Seattle to become a massive, major seaport?  What are the losses?  Profits will not be distributed to taxpayers, that is certain.  A risky, unnecessary boondoggle, IMO.

  • Steve March 7, 2019 (10:39 am)

    I emailed the “alliance” , from my fancy DHS contractor email address, wanting to know how the vote went. I got no response. Nothing has been updated on their website.

  • WSB March 8, 2019 (12:17 am)

    Well, I can’t help you with getting them to send you an official answer but as linked in our followup story, they did update their website to reflect the bid authorization vote passing, This is the page containing that update.

    https://www.nwseaportalliance.com/about/strategic-plan/t5

Sorry, comment time is over.