First #Realign99 closures now less than 1 week away

Time for the countdown to rev up. The first closures as part of #Realign99 – the work that’s necessary for the Highway 99 viaduct-to-tunnel transition – are now less than 1 week away:

10 p.m. Friday, Jan. 4: Stadium ramps close

Northbound SR 99 on-ramp at South Royal Brougham Way closes (near stadiums; connection to I-90 and I-5).
Southbound SR 99 off-ramp at South Atlantic Street closes (near stadiums; connection to I-90 and I-5).

That’s exactly one week before the Alaskan Way Viaduct is permanently closed at 10 pm Friday, January 11th. The full timeline is here.

5 Replies to "First #Realign99 closures now less than 1 week away"

  • Abcgirl December 29, 2018 (3:28 pm)

    Anyone concerned that the opening of the tuunel has yet to be determined. Everything else has a time frame except the most critical element . I am a skeptic of this process coming off without a major hiccup. So far timeframes have been less than accurate

    • Svejk December 29, 2018 (4:17 pm)

      “Major  Hiccups Are Us”–the Seattle City Council

      • WSB December 29, 2018 (4:22 pm)

        The realignment work is a state project, as is the tunnel, not the city.

  • West Seattle Hipster December 29, 2018 (4:27 pm)

    I would not be surprised if the tunnel opens earlier than planned.  WSDOT usually gives a conservative estimate but usually opens ahead of schedule.

  • dsa December 29, 2018 (5:21 pm)

    Contract probably has incentives.