One week ago tonight, we reported on Seattle Public Utilities crews investigating a sewer-line problem at 41st/Genesee on the north side of The Junction, next to Seattle Lutheran High School. Tonight, we have word from SPU that they’ll be doing repair work this weekend, scheduled for 7 am-6 pm both days unless they finish early – and if it takes longer, it’ll continue into Monday. They determined the pipe break is at the top of the slope, and closed the walkway between 41st and Genesee until repairs are complete, as well as installing a pump bypass system. To fix it, SPU’s Marieke Rack says, “SPU will stage crews and equipment in the 41st Avenue SW dead-end above Genesee Street. SPU’s excavation area is approximately 28’ south of the maintenance hole (which is near the jersey barrier). We will have 2 dump trucks, an excavator, and a crew truck and trailer on site.”