Home stretch for Murray CSO project across from Lowman Beach

October 7, 2015 9:31 pm
|    Comments Off on Home stretch for Murray CSO project across from Lowman Beach
 |   Environment | West Seattle news

(King County photo)
A milestone for the Murray Combined Sewer Overflow Control Project across from Lowman Beach Park – the tank is complete, and construction is starting for the building housing it. It’s been eight years since community members started hearing about the need for a project to reduce overflows into Puget Sound, almost five years after the announcement of the plan to locate it on what was a residential block, and almost two years since site work began. Announced tonight by the King County Wastewater Treatment Division:

King County’s contractor finished the concrete work for the Murray CSO Control facility’s one million gallon underground storage tank. Building the storage tank required some of the most intense activity on the project. King County and its contractor deeply appreciate the community’s patience while crews built the tank.

The facility building will have three rooms to house mechanical and electrical equipment. It was designed to follow the slope of Lincoln Park Way SW behind it. The building will be 20 feet tall at its highest point. Construction of the facility building will continue into Spring 2016.

Work to connect the underground storage tank to the Murray Pump Station will continue while the building is constructed. This work will increase congestion and cause traffic delays of up to 15 minutes and parking restrictions on the 7000 block of Beach Dr. SW. Please stay safe. Follow
the directions of flaggers and signs when near the site.

The project is intended to dramatically reduce the number of overflows from the Murray Pump Station at Lowman Beach, from an average of five per year – and five million gallons total – down to no more than one.