One week after our in-depth update on the Spokane Street Viaduct Widening Project – which has been closing the east end of the West Seattle Bridge most weeknights lately – there’s a milestone of sorts: Crews are starting to install long-delayed steel girders that SDOT said had been holding up the new 1st Avenue South on/offramp. Brad tipped us off via Twitter:
@westseattleblog You might already know this, but … they’re re-starting work on the 1st ave s onramp. A sight for sore eyes.
— brad nelson (@bradnelson) February 15, 2012
Before stopping nearby for the photo you see above, we sent an inquiry to SDOT, asking if the resumption of work meant those girders were finally arriving. Spokesperson Rick Sheridan‘s reply:
You are correct. The installation of the steel girders for the First Avenue S on- and off-ramp is now underway.
The contractor working for the Seattle Department of Transportation on the Spokane Street Viaduct Widening Project began this week installing the steel girders necessary for constructing the First Avenue S on- and off-ramp. The installation is taking place during the night.
After much delay, half of the girders required for the ramp arrived from their source in Montana and the contractor expects it will take several weeks to install these. The other half of the girders has not yet arrived. With the full installation of these girders, the remaining construction of the ramp can proceed.
The ramp is expected to be available as an offramp sometime this spring – but not as an onramp from 1st until the project is virtually complete, probably late July. Meantime, construction closures continue – the newest update is here – and keep in mind, this is SEPARATE from the project at the WEST end of the WS Bridge, which is the Fauntleroy Expressway Seismic Retrofit Project, responsible for closures of its own (including all day this coming Sunday). That project too should be complete this summer.
| 23 COMMENTS