Tale of two pits: Highway 99 tunnel-machine rescue update; Murray CSO tank site overview

October 20, 2014 at 12:47 pm | In Transportation, Utilities, West Seattle news | 15 Comments

Whole lot of digging going on around the city these days. Two new views:

TUNNEL-MACHINE RESCUE: WSDOT says digging has officially begun for the pit they’ll use to pull up the Highway 99 tunnel machine’s cutting head for repairs – the photo is a screengrab from one of their live construction cameras. Tons of info in this update. The pit will be 120 feet deep, which is twice as big as the West Seattle pit we’re updating next:

OVERFLOW TANK PIT, HALFWAY THERE: Last Wednesday night, in our coverage of the Morgan Community Association‘s quarterly meeting, we reported the county’s update on the excavation by Lowman Beach: They’re halfway to what’s expected to be a 60-foot-deep pit for the million-gallon Murray Combined Sewer Overflow Control Project storage tank. (It’s known as Murray after the nearby street, which also is namesake for the pump station beneath the southeast side of Lowman Beach Park.) So we went over for a look (map). We’re also checking on whether the delayed start of the extra digging sessions on Saturdays means a delayed end date.

ADDED 3:28 PM: According to county Wastewater Treatment Division spokesperson Doug Marsano, “Crews are making good progress – they’re over 40 feet down now (about 2/3rds of the way) – but the rains forecasted for this week could hinder their progress. Currently, the project team expects to work 2 more Saturdays, extending into early November.”

Fauntleroy Community Association invites neighbors to talk with city leaders about transportation challenges

October 17, 2014 at 2:48 pm | In Fauntleroy, Transportation, West Seattle news | 1 Comment

Ongoing transportation/traffic concerns in Fauntleroy will get an airing in front of city reps including SDOT’s new director in three weeks: Thursday, November 6th, is the time/date just announced by the Fauntleroy Community Association for its long-in-the-works community conversation about issues from speeding to sidewalks to parking, and beyond. FCA president Mike Dey says SDOT director Scott Kubly, DPD director Diane Sugimura, Mayor Murray’s transportation adviser Andrew Glass Hastings, and City Council reps have all confirmed they’ll be there, 7 pm at The Hall at Fauntleroy.

Making 35th SW safer: SDOT adds second community meeting

October 17, 2014 at 10:22 am | In Safety, Transportation, West Seattle news | 13 Comments

(WSB photo from 2008: One of many safety rallies/demonstrations on ‘I-35′)
Just in from SDOT: Two meetings are now planned to kick off the 35th SW safety-improvement program. The 6:30-8 pm meeting next Wednesday (October 22nd) at Neighborhood House’s High Point Center was announced back in August; now, they’re adding a meeting on Tuesday, October 28th, 3:30-5 pm at Southwest Branch Library. Plans for the “multi-year” safety project were first announced back in February, after years of crashes and concerns along what’s been dubbed “I-35.”

Touring the Junction/Triangle ‘walkshed’: Proliferation of plans

October 16, 2014 at 12:51 pm | In Development, Transportation, West Seattle news | 8 Comments

By Tracy Record
West Seattle Blog editor

Seattle Comprehensive Plan

West Seattle Junction Hub Neighborhood Plan

West Seattle Triangle Streetscape Concept Plan ..

Seattle Transit Master Plan

Seattle Bicycle Master Plan

Seattle Pedestrian Master Plan

Seattle Right of Way Improvements Manual

Seattle Pedestrian Retail Areas plan

Fauntleroy Boulevard plan

One thing was clear during last Saturday’s “walkshed” tour of the Junction/Triangle area, with Seattle Planning Commission reps listening to local community reps: There’s no shortage of plans and documents covering the area, but there’s a shortage of understanding in how they interact, interface, intersect, and what they mean.

The tour itself was linked to the Planning Commission’s ongoing work on the city Comprehensive Plan update, dubbed Seattle 2035. The next big milestone for that is the environmental-impact statement, expected to be out early next year. And this is no bureaucratic bit of wonkiness to ignore: As was pointed out at the start of Saturday’s event, this type of discussion preceded the 1990s-generated plan for “urban villages” including The Junction/Triangle – much of which is only now coming to pass, as was underscored by the current, future, and recent development sites passed (and often discussed) along the way.

But the topic wasn’t just the dense heart of the Junction/Triangle, but also its single-family zones – like a stretch of 40th south of Edmunds and the major project sites bordering it on the north.

For backstory on the tour, see our coverage of last month’s Junction Neighborhood Organization meeting (which included a slide deck setting the stage). To see what happened during the tour – read on:

Click to read the rest of Touring the Junction/Triangle ‘walkshed’: Proliferation of plans…

Update: West Seattle Transportation Coalition votes to endorse transit-funding measure, but no position on monorail

October 14, 2014 at 9:06 pm | In Transportation, West Seattle news, West Seattle politics | 11 Comments

Two toplines so far from tonight’s West Seattle Transportation Coalition meeting: WSTC voted to endorse the bus-funding measure on the November 4 ballot, officially Transportation Benefit District Proposition No. 1. And it voted NOT to endorse the monorail measure on the ballot, officially Seattle Citizen Petition No. 1. More to come.

ADDED WEDNESDAY MORNING: More toplines from the WSTC meeting:

Click to read the rest of Update: West Seattle Transportation Coalition votes to endorse transit-funding measure, but no position on monorail…

Followup: RapidRide on California in The Junction? 2 briefings

October 7, 2014 at 2:06 pm | In Transportation, West Seattle news | 17 Comments

Back in August, following up on a reader tip, we reported that SDOT is considering moving the RapidRide C Line route in The Junction onto California between Edmunds and Alaska. At the time, SDOT told us “outreach” was planned in the fall. Now that it’s fall, what’s the status? we asked SDOT’s Marybeth Turner, who replied:

SDOT staff is scheduled to meet with the West Seattle Junction Association on Oct. 22, and the SW District Council on Nov. 5 about California and Alaska, including the needs of cars, buses, and pedestrians.

In November they will mail information to some of the nearby businesses and residents, and talk in person to some of the businesses.

Turner says the recent re-sequencing of the California/Alaska signal (reported here Saturday) is NOT related to this – she describes that as having been done to improve “safety,” and is still working to get us more information from department engineers.

UPDATED P.S., CORRECTING MEETING INFO The aforementioned WSJA briefing is for the group’s membership (businesses in The Junction), but the Southwest District Council meeting is open to everyone, 6:30 pm Wednesday, November 5th, at the Senior Center of West Seattle (Oregon/California).

Seattle, Tacoma ports to ‘unify management’ with Seaport Alliance

October 7, 2014 at 12:07 pm | In Transportation, West Seattle news | 15 Comments

(Photo by Peter West Carey, shared via Twitter)
On Thursday, the West Seattle Chamber of Commerce hosts Port of Seattle co-president Stephanie Bowman at its monthly lunch meeting. Questions about the future of shuttered Terminal 5 were already expected – and now there’s something new: Today’s announcement that the Seattle and Tacoma ports are forming a “single Seaport Alliance.” Here’s the news release from the Port of Seattle:

The Seattle and Tacoma port commissions plan to unify the management of the two ports’ marine cargo terminals and related functions under a single Seaport Alliance in order to strengthen the Puget Sound gateway and attract more marine cargo for the region.

The Seaport Alliance will manage marine cargo terminal investments and operations, planning and marketing, while the individual port commissions will retain their existing governance structures and ownership of assets.

This unprecedented level of cooperation between the state’s two largest container ports is a strategic response to the competitive pressures that are reshaping the global shipping industry.

Click to read the rest of Seattle, Tacoma ports to ‘unify management’ with Seaport Alliance…

Reader report: New sequence at ‘Walk All Ways’ intersection

October 4, 2014 at 10:22 pm | In Transportation, West Seattle news | 24 Comments


(“Walk All Ways” signage in 1956; click image to see full-size Seattle Muni Archives photo)
It’s not often news when a traffic signal is tweaked. But in this case, we’ve now received several reader reports of a sequencing change at the most-famous intersection in West Seattle – and since tomorrow is usually its busiest day of the week, with Farmers’ Market shoppers and brunchgoers (among others), we’re sharing the FYI. First word came from Kathleen, who explained:

The sequence of red/ green lights and “walk” signs has changed sequence. I walk up to the Junction nearly every day and it has always been: green light going east on Alaska across Calif.: then green light going west; and then green light for the traffic going north/south on Calif; THEN the walk all 4 ways signal.

(Thursday) I couldn’t figure why so many cars were running through the intersection at the wrong times. I almost missed going across the street because I was waiting for the north/south traffic to go before me. It has been changed so the 4-way walk is now BEFORE north/ south cars can go. Confusing to anyone who has done it the old way forever!

We’ll be asking SDOT about this on Monday.

P.S. The history of “Walk All Ways” here is part of this HistoryLink.org essay about The Junction, which says it was installed in 1952, removed in 1974, brought back in 1988.

5 ‘most pressing transportation issues,’ as the West Seattle Transportation Coalition sees it, starting Year 2

September 28, 2014 at 10:01 pm | In Transportation, West Seattle news | 35 Comments

The West Seattle Transportation Coalition is about to start its second year. After one year of meetings, conversations, discussions, and outreach, WSTC has announced a list of “the five most pressing transportation issues for the West Seattle peninsula, which are within the power of the City of Seattle to directly address and resolve,” and sent a letter about them to city leaders.

First, the WSTC list:

#1

(WSB file screengrab of SDOT camera looking toward bridge’s offramp to 99)
Expand vehicle capacity from the West Seattle Bridge to SR-99.

#2

(Photo by Long B. Nguyen)
Develop a “West Seattle Peninsula” emergency relief plan.

#3

(WSB file photo of the sign that marked the former 4th Ave. onramp spot until 2008.)
Increase access to the westbound Spokane St. Viaduct from SODO.

#4

(City file photo of Lander tracks)
Complete the Lander Street Overpass.

#5

(December 2013: De-icer-slick, closed-to-traffic bridge; WSB photo by Christopher Boffoli)
Immediate mitigation of traffic events to West Seattle peninsula chokepoints.

WSTC says it has sent a letter outlining “… these issues, possible resolutions, and (calls) for action …” to Seattle Mayor Ed Murray, City Council President Tim Burgess, and City Council Transportation Committee Chair Tom Rasmussen. It asks for a response with the “plan of action” by January 9, 2015. You can read the letter on the WSTC website, or below:

Agree? Disagree? Get involved! The WSTC meets on second Tuesdays and invites all to its next meeting, October 14th, 6:30 pm, at Neighborhood House’s High Point Center.

SIDE NOTE: This will also be a busy season on some of the problems for which WSTC and local neighborhood councils already have pushed for action – next launch is the 35th Avenue SW Road Safety Corridor project, with a community meeting October 22nd.

Bus a no-show? Metro staff reductions leading to missed trips

September 23, 2014 at 9:45 pm | In Transportation, West Seattle news | 57 Comments

None of the Metro routes scheduled for service cuts or deletions starting this Saturday are in this area. But you might have experienced some related, if temporary, effects of Metro getting ready for reductions. WSB reader Holly did: “I thought I’d pass this along since I wasn’t aware it was happening, until it happened to me. The 56 bus route from Admiral didn’t come last week and this is the response I got from Metro – basically that routes here and there are being canceled due to driver shortages.” Ahead, the reply Holly received after e-mailing a comment to Metro, and the results of our followup:
Click to read the rest of Bus a no-show? Metro staff reductions leading to missed trips…

Miss the Fauntleroy (Way) Boulevard open house? Here’s what you missed, and what’s next

September 23, 2014 at 6:20 pm | In Transportation, Triangle, West Seattle news | 5 Comments

6:20 PM: As of 6 pm, midway through the two-hour SDOT open house for the Fauntleroy Way SW Boulevard project, about 45 people had dropped by. You still have until 7 pm to go to the Senior Center of West Seattle and get a closer look at the newest renderings for how this project would change Fauntleroy Way between SW Alaska and 35th SW (they’re also now available on the official webpage), with project manager Thérèse Casper and others standing by to answer your questions, as well as several ways to comment (from sticky notes to computer terminals).

The project is on its way to 60 percent design; if the $500,000 that’s in the mayor’s budget for the remaining 40 percent is approved, that will proceed, and then the city has to figure out how to pay to build the project’s features.

7:02 PM: Here are the renderings that were up on boards around the room at the meeting:

This is the official updated project info-sheet:

Something to say? Say it sooner rather than later – here’s one way to do that. Casper says they’re continuing to meet with local businesses and organizations and have already met with some businesses multiple times, to go over points of concern.

Ferry update: WSF down one boat, trying to catch up, on Fauntleroy-Vashon-Southworth route

September 20, 2014 at 9:15 pm | In Transportation, West Seattle news | 2 Comments

M/V Tillikum remains out of service on Washington State Ferries‘ Fauntleroy-Vashon-Southworth route, explained only as “due to operational constraints.” In the newest update, WSF says it’s adding more sailings on M/V Evergreen State to try to catch up. This all comes on the eve of WSF’s fall schedule taking effect tomorrow; no word yet on whether they’ll be back to 3 boats by then.

What’s along ‘Fauntleroy Boulevard’? Highlights of JuNO’s briefing, before you get a look at next Tuesday’s community open house

September 19, 2014 at 8:43 pm | In Transportation, Triangle, West Seattle news | 12 Comments

It’s been six years in the making, but the “Fauntleroy Boulevard” plan is still in the “early design” phase – which is why, if you are interested in the future of Fauntleroy Way between the bridge and SW Alaska, you’re going to want to go to next Tuesday’s community meeting.

SDOT’s Fauntleroy Boulevard Project manager Therese Casper and consultant Mike Hendrix (from Perteet) came to this week’s Junction Neighborhood Organization meeting for one last community-council-level briefing before that meeting, which, by the way, will be in open-house format, so don’t worry if you can’t get there right when it starts at 5 pm – drop in for a look at the plans any time before 7 pm.

We’ve written about it before – going back to 2008 – and Casper noted that its origins go back even further, to the West Seattle Junction Plan of 1999, and now the Bicycle Master Plan‘s goals have been folded in, designating this as an area for protected bicycle lanes, as well as the “community needs” in the Triangle Streetscape Plan, and enhancement of Fauntleroy Way’s role as a gateway to West Seattle.

The Fauntleroy Boulevard plan has reached 30 percent design, and has funding through 60 percent design. The city budget process that kicks into high gear next week, with Mayor Murray presenting his proposal on Monday afternoon, will determine what happens next – will there be money to finish the design and build the project?

Its typical cross-section is the same one we first showed in July: 6′ sidewalks, 6′ protected bike lanes (asphalt), landscape strip, outside lanes of roadway maintained at 12′ (to facilitate freight needs), 10′ travel lane inside, then middle turn lane OR planted median. You can see it and the block-by-block concept on this info-sheet, also from July:

Here’s the latest on some key points – with many more details promised at next Tuesday’s open house:

Click to read the rest of What’s along ‘Fauntleroy Boulevard’? Highlights of JuNO’s briefing, before you get a look at next Tuesday’s community open house…

TUNNEL TOUR: Follow along on an 8-flight descent into what’s already been dug

September 19, 2014 at 2:42 am | In Alaskan Way Viaduct, Transportation, West Seattle news | 35 Comments

(EDITOR’S NOTE: Even if you agree with the advocacy group that has declared the Highway 99 tunnel a “boondoggle,” nine months after its boring machine stalled, you might be interested in a look at what’s already been done and what’s continuing to progress even before the upcoming repairs. WSDOT invited media to tour the site Thursday, and photojournalist Christopher Boffoli went on behalf of WSB. Here are his photos and narrative of how it went.

Photos, video, and story by Christopher Boffoli
Reporting for West Seattle Blog

The meeting point for our tour was an entrance at the end of South King Street just under the Alaskan Way Viaduct. After being issued safety clothes (hard hat, safety glasses, gloves, and reflective vests) we were greeted by Chris Dixon, Project Manager for Seattle Tunnel Partners, who led our group of about 7 or 8 journalists over to one of the engineering and orientation trailers.

This was a small meeting room with a lot of colorful schematics and cross-section geologic diagrams on the walls:

Dixon explained that – while the Tunnel Boring Machine (TBM) is idle – work is advancing at both the north end of the site (where a cut and cover tunnel is being prepared in the area where the TBM will eventually emerge) and the south end of the site, near the stadiums, where the future roadways are being prepared.

There is also a great deal of activity inside the existing tunnel itself. On a whiteboard Dixon drew a cross-section of the tunnel and explained how crews are busy installing structures called corbels along the tunnel floor:

These concrete structures are essentially footings that will bear the weight of the straight interior tunnel walls and the concrete road decks (southbound traffic above and northbound traffic below) that vehicles will drive over.

He said that by the time the TBM resumes its digging, they expect to have 450 feet of the tunnel’s interior complete. Dixon said that this work was originally set to happen later but that they have reconfigured the schedule while work is underway to repair the TBM.

We were joined by Matt Preedy, Deputy Program Administrator, WSDOT (and a West Seattle resident).

All of the journalists were issued numbered brass tags which were recorded on a ledger and that we pinned to our vests. As we left the engineering trailer and entered the site, there were a number of large boards with numbered dots painted on them. Dixon and Preedy went to the boards and attached their own brass tags to them.

They didn’t take the time to explain, but those ‘pit tags’ (also called check tags) are a system employed for hundreds of years to keep track of who is working inside a mine, or in this case, a tunnel. One of the first things we saw (at ground level) were piles of curved, pre-cast concrete panels that are arranged in place behind the TBM.

Bolted together into rings, they form the very strong, outer tunnel walls. Their tight-fitting gaskets are designed to keep ground water at bay.

There are ten panels in each ring and there are to be 1,450 rings in the complete tunnel.

We walked out over a concrete gantry from which we could look down on the launch pit below. To the south were the almost completed roadways that someday would carry traffic in and out of the SR-99 tunnel:

Turning around, we could see the entirety of the launch pit and the tunnel entrance at the end of it.

We descended about eight flights of steep, metal stairs to the floor of the site.

Behind us (to the south) was a completed section of cut-and-cover tunnel, with its neat, square walls, unlike the circular structure of the bored tunnel that we were about to tour.

Construction material (mostly rebar) was everywhere:

Along the sides of the pit, workers were busy covering the walls with Spray-Crete, a light, liquid form of cement.

To our right we could see the below-ground part of what we were told would become the South Operation Building. Water also seemed to be ubiquitous, seeping in all over the walls of the site.

Dixon said that, though some of it might be from nearby Elliott Bay, most of it was fresh groundwater.

We descended a ladder to an even lower section of the launch pit, level with the bottom of the tunnel.

Walking inside the tunnel at last, we could see large red concrete forms and workers installing structural re-bar along the bottom sides of the tunnel.

This is the corbel work we were told about.

Beyond the equipment and activity near the entrance of the tunnel, it was only when you walked a bit further into the tunnel that could you appreciate the impressive size of the space.

It was here that you could also appreciate the intricate puzzle of curved concrete panels.

Overhead was a large yellow ventilation shaft that brings fresh air into the deepest part of the tunnel and that can be reversed in an emergency to pull smoke from a fire out of the tunnel. Also above was part of the long conveyor belt on which tailings and slurry are removed to awaiting barges. Dixon explained that, as the TBM advances, sections of conveyor belt are added.

By the end of the project, the belt will be as long as the tunnel itself.

Outside in the open pit we had seen piles of coiled belt sections waiting to be installed in the future.

The first part of the TBM you see is the white-painted, rear superstructure of the
300 foot long trailing section.

Massive wheels support the entire machine, which includes all of the systems of wires and pipes for power and to pump chemicals and grout towards the face of the TBM. As you move forward, you encounter the system that receives the curved panel sections, picks them up, orients them to the proper position and location for installation when they are needed.

Moving forward still, you approach the section of the TBM that is behind the cutting face.

Everything there seems covered with some form of water or mud. There are hazards to footing and low clearances, making it a challenge to decide if you should watch your head or where you step. Everything was lit with fluorescent tubes, giving it a bright – if slightly green – cast. As we arrived to the most recently-installed ring of curved concrete sections, at the very bottom, Dixon and Preedy showed us the enormous pistons that the TBM uses to push against the edge of the course of concrete rings to advance itself forward.

As politicized as the bored tunnel has been and continues to be in Seattle, I must say that standing in the bowels of the machine, it is difficult not to be in awe of the scale and size of the complex machinery, the intricate tapestry of conduits, hoses, pistons, motors, fittings and beams – the sheer audacity of the technology involved in pushing through the earth blindly at 100 feet below sea level.

It is a level of technological complexity that I have only before seen when watching a Ridley Scott film set inside of a spaceship. It did not seem like a place that a group of human beings should be standing. And it was even more incomprehensible that people had designed and built it.

We climbed narrow staircases through a maze of passageways to see where the muddy tailings from the cutting face begin their journey out of the tunnel.

On another level we visited the control room with the screens and consoles from which workers can manage and monitor all aspects of the TBM when it is in operation.

Dixon explained that the numbers we saw on the primary displays indicated just over two bars of pressure (regular atmospheric pressure is one bar; most commercial espresso makers operate at 10-15 bars of pressure). Even though the TBM was not running he said that the instruments generally don’t read much more than that. He added that – when in operation – the cutting face of the TBM isn’t even all that loud, though Preedy added that all of the motors that power the conveyor belts for the removal of tailings do make the back of the machine very noisy.

Though the TBM was idle, Dixon said that workers are kept busy “exercising” and maintaining many of the parts of the machine that might atrophy or otherwise fall into disrepair if left sitting for a long time. It wasn’t uncomfortably warm inside the heart of the machine, though Dixon said that when the TBM is in operation it does get quite hot down there as the heat of friction is transferred through the cutting face to the surrounding spaces. Heat played into what went wrong, and what’s being fixed, he explained:

Adjacent to the control room – still inside the heart of the TBM structure – was a break room that, with coffee maker, microwave oven, long lunch tables, etc. would look at home in any factory. It was hard to believe it was at the center of an incredibly complex machine deep underground.

Nearby we saw a collection of cutting heads, each weighing 1500 pounds, that could be attached to an overhead rail for transport to the front of the cutting face for replacement. Various cutting heads are used, depending on the soil conditions.

The “rippers” we saw are best suited for the type of loose glacial soils that are expected in this section of the project.

At the very front of the TBM we could see the large blue motors that individually power each of the cutting heads.

On the same level we could see the central drive shaft, painted light green. And to the sides were large pressure vessels through which men and equipment could safely transition to the pressurized area on the other side of the cutting face, if needed.

With our tour complete we walked back through the various stairways and passages, back down to the tunnel floor at the rear of the TBM’s trailing gear, and out the way we came.

The palms of my light-colored gloves – which had honestly seemed like overkill at the start of the tour – had somehow become darkened.

After we had climbed the fairly treacherous ladders and countless treads of metal stairways, we were led back to the engineering and orientation trailers where, one by one, we turned in our numbered brass tags and were signed out of the ledger.

What happens next in the repair process? Here’s the latest update on the project website. For more on the project’s status, here’s what our partners at The Seattle Times published post-tour.

Port possibilities, crosswalk concerns @ Delridge District Council

September 18, 2014 at 3:15 pm | In Delridge District Council, Transportation, West Seattle news | 4 Comments

(Terminal 5, photographed earlier this week by Don Brubeck)
A triple bill of transportation-related guests at last night’s Delridge Neighborhoods District Council meeting – Seattle Port Commissioner Courtney Gregoire, City Councilmember (chairing its Transportation Committee) Tom Rasmussen, and just-confirmed SDOT director Scott Kubly, who, in his third West Seattle appearance in two weeks, heard about safety concerns outside two local schools.

First: With the expanse of closed-and-idle Terminal 5 in the line of sight for thousands of West Seattleites daily, its future was a major topic for Commissioner Gregoire.

Click to read the rest of Port possibilities, crosswalk concerns @ Delridge District Council…

As-it-happened coverage: Metro Transit budget briefing downtown; cuts beyond next spring now pushed back to 2016

September 17, 2014 at 10:02 am | In Transportation, West Seattle news | 22 Comments

(WSB photo of Dively & Desmond, substituted for originally posted Twitter image)
10:02 AM: We’re at King County’s King Street Center, where Metro Transit general manager Kevin Desmond and the county’s budget boss Dwight Dively are briefing the media on what County Executive Dow Constantine will propose for Metro in his budget, due out next Monday. Since Metro is of special interest to our transportation-challenged peninsula, we’re here to report the toplines live.

First, from the news release handed out:

*Beyond the September 2014 (no West Seattle routes involved) and February 2015 (that plan announced two weeks ago includes, for West Seattle, deleting Route 22 and changing the 21, 116X, and 125) cuts, 80,000 hours in cuts (half the March number) are suggested for March 2016 – so much in play, they aren’t saying which routes that might affect.

Dively says they’re creating budget efficiencies through health-care costs, saving $3 million for transit over the next two years. Also, diesel prices have gone down. Sales tax, though, he describes as “volatile” – and the forecast they’re using now came out in August, and isn’t much different than what they had in March.

Desmond is recapping some of the steps Metro has taken in recent years and insisting “We have not stopped for a second trying to find ways to keep service on the road, to stretch our dollars further, whether from our expense budget … or capital budget … We don’t want to cut service. Our mission is to transport people every single day …”

Here’s what he says has changed, leading to savings that in turn mean fewer cuts:

*Buying 40 fewer buses, saving $40 million in capital budget
*Negotiated better prices on buses they are buying, saving $50 million (also capital program)
*Job injuries/worker comp claims/lawsuit claims – saving $13 million
*Vehicle maintenance “process improvement” – $2 million
*Reducing service means fewer drivers, $3 million less spending, 335 jobs lost at Metro over next 2 years
*Fuel conversion saving $1 million
*Paratransit costs, “most expensive product that Metro operates” (Access service), $7 million savings
*Full list in news release

So bottom line, 400,000 service hours to be cut, instead of once-forecast 550,000. But Desmond says they know that’ll still be painful. First 151,000 hours kick in September 21st.

10:15 AM: Now he gets to the Seattle transit-money ballot measure in November. “If the Seattle measure passes, the February service changes will automatically be deferred until June 2015 to allow Metro and the city time to enter into service contracts – all of the cuts would be deferred, not just the Seattle cuts.” He says they still look forward to adding service sometime. August ridership figures show a 3 percent increase, and, says Desmond: “At the same time we are reducing the system, what we really should be doing is growing.” He acknowledges overcrowded buses around the county, unreliable buses because of traffic – “We need to solve these problems and this budget doesn’t allow us to do that.” He says the system is 900,000 hours short of what might help fix that.

Now Q/A – what about the transit workers who rejected wage freezes, how does that figure into this? Desmond says the situation now goes to binding arbitration. If the transit workers had accepted the freezes, that would have saved $8 million – equal to 80,000 hours of service cuts. “We do not expect to get an arbitration decision until the second quarter of next year,” Desmond said. Otherwise, the budget currently incorporates the “basic cost-of-living increase” for those and other workers.

Next question, “How do you respond to those who say you’re using scare tactics to get people to approve a tax increase?” Desmond points to the fact “we’ve been talking about this for six years. … We’ve not been hiding this from anybody through that entire six-year period.” (Editor’s note: Here’s a 2008 mention on WSB.) He talks about committees and task forces that have been going through the system and how it works, “totally out in the open” over those years. “We were the only transit system in this state in 2011 … that convinced the state Legislature to give us another tool to keep service on the road.” Though they’ve figured out how to save 150,000 hours in cuts, he says 400,000 hours worth are still painful, and “six years of kicking the can down the road in terms of stopgap measures and one-time savings … we’ve got to put a stop to that. … We don’t want to continue to lurch back and forth with the public.” He says they’re still at risk of having to keep cutting if the economy has a downturn at this point.

Desmond says they’re hoping that they can get to the point where they can “look at making some improvements” in Seattle lines that are currently overcrowded. Should downtown businesses chip in with head taxes or in other ways? Desmond says he doesn’t want to “get into that” but that there are already ways that the business community is helping, including pre-paid fare products. Dively also points out that head taxes are a city-only tool – not available to counties, in our state – and it’s up to the city to figure out how it wants to raise money. Desmond, then, turns back a question meant to elicit a “why should Seattle voters approve the ballot measure?” answer. He just mentions that the area is growing and transit should be growing, not contracting.

10:29 AM: Desmond mentions SDOT’s new director Scott Kubly, saying that Kubly is “really excited” about finding ways to improve the right of way for buses so they don’t get stuck in traffic and therefore delayed as often.

We ask about fare increases – Desmond points out the one scheduled for March of next year, and beyond that, he says that it would likely be a dialogue with the county council since the executive is not proposing another fare increase before 2018. He mentions the oft-cited stat that Metro’s basic fare will have doubled since 2008, when next year’s increase kicks in (at the same time a new low-income fare takes effect). “We always have to be thinking hard and struggling to find the right pricepoint …” appealing to “discretionary” riders as well as those who have no alternative.

10:35 AM: Briefing over – full complement of regional media was here too. If you want to read the full news release, it’s here.

Scott Kubly confirmed as SDOT director, due back in West Seattle at Wednesday’s Delridge Neighborhoods District Council meeting

September 15, 2014 at 3:02 pm | In Delridge District Council, Transportation, West Seattle news | Comments Off

Scott Kubly has just been officially confirmed as the new Seattle Department of Transportation director. He’s made two official West Seattle appearances already, both covered here – last week’s West Seattle Transportation Coalition meeting (link includes our video) and the September 3rd Southwest District Council meeting. If you have a question or suggestion for Kubly, you have one more near-future chance in West Seattle: He’s scheduled to be at the Delridge Neighborhoods District Council meeting this Wednesday (September 17, 7 pm, Youngstown Cultural Arts Center at 4408 Delridge Way SW).

Traffic alert: Paving on East Marginal Way, north of the bridge, next week

September 12, 2014 at 4:00 pm | In Transportation | 1 Comment

A much-used West Seattle-downtown route, particularly for bicycle riders, is set for paving work next week, according to this announcement from SDOT:

Crews from the Seattle Department of Transportation will pave in the 3100 block of East Marginal Way South [map] on Wednesday, Sept. 17 from 8 a.m. to 3 p.m. and on Thursday, Sept. 18 from 8 a.m. to 6 p.m., weather permitting.

On Wednesday, bicycles may use the designated bike lane. On Thursday bicyclists may ride on the sidewalk, being cautious of pedestrians and giving pedestrians the right of way. For information on bus service, look for Rider Alert notices at bus stops.

This is an area where a deadly bicycle/truck collision last year led to city promises of safety improvements.

New leader announced for Washington State Ferries: Lynne Griffith

September 10, 2014 at 9:55 am | In Transportation, West Seattle news | 9 Comments

A new leader for the state ferry system is on the way: Lynne Griffith, currently CEO of Pierce Transit, a job she had held for eight years and had previously said she would leave at year’s end. Griffith’s appointment was announced this morning by state Transportation Secretary Lynn Peterson. The official news release notes that Griffith will be the first woman to serve in the role of Assistant Secretary for WSDOT’s Washington State Ferries division, and that she has more than 35 years of experience in the transportation industry. The previous assistant secretary, David Moseley, resigned six months ago after six years. Griffith starts next month. (Photo courtesy WSF)

West Seattle Transportation Coalition gets ‘prioritization’ promise from new SDOT director Scott Kubly; also hears about citizen’s T-5 idea, November ballot measures

September 9, 2014 at 9:06 pm | In Transportation, West Seattle news | 20 Comments

(ADDED WEDNESDAY AM: Our video of SDOT director Scott Kubly’s hour-long Q/A)

By Tracy Record
West Seattle Blog editor

For the second time in a week, SDOT’s new director (confirmation pending) Scott Kubly was in West Seattle to answer questions – this time, from the West Seattle Transportation Coalition.

Among other things, Kubly said that one of the best ways his department can serve this area and others is to be clear about prioritization – what it can do, what it can’t do.

The 2 1/2-hour meeting ranged across a wide variety of other topics as well, including the two transportation-related measures on the November ballot, and a citizen proposal for the currently idle Terminal 5 site.

First, Kubly: After a brief introduction, he said that at any Department of Transportation, “safety’s going to be the first priority,” yet there have been five fatalities in the first three weeks he’s been on the job. “Where I come from is … wanting to protect the most vulnerable users of the transportation system. … I also think the city is growing tremendously quickly … it reminds me a lot of DC in that regard, similar sizes, similar growth rates.” Growth means the opportunity for more-walkable communities, he said, “but not without challenges … it stresses the transportation system, so what we need to do is .. how to make our transportation system work more efficiently.”

That means “giving people choices in how they get around the city.” People who walk to work, for example, have been shown in research to be the happiest people, Kubly said, but when in a car, he said, people somehow feel safe behaving aggressively, and he feels that’s because they don’t have a choice, so if they have a choice, they’ll feel happier. But he also recognizes that “most people are at one time or another going to have to drive someplace … it’s very rare that you can do everything (without driving).”

DC, he said, has more people but fewer cars than it used to have, he points out. And he talks again about options, enabling people to, for example, perhaps have one car instead of two. Regarding why people get frustrated with government services: “A lot of it comes down to choice.”

Click to read the rest of West Seattle Transportation Coalition gets ‘prioritization’ promise from new SDOT director Scott Kubly; also hears about citizen’s T-5 idea, November ballot measures…

Citizen idea for closed, empty Terminal 5 on Tuesday’s West Seattle Transportation Coalition agenda, along with new SDOT director

September 5, 2014 at 10:39 pm | In Transportation, West Seattle news | 31 Comments


This West Seattle view, tweeted today, shows a stark look at what so many continue to notice, especially driving westbound on the high bridge – the emptiness of the port’s Terminal 5, now in its second month of closure. It’s a discussion topic on next Tuesday night’s West Seattle Transportation Coalition agenda. But in case you’ve missed the backstory:

*In June, the Port Commission approved closure as the first step toward “modernization”
*The final ship, for now, called at T-5 in late July
*Commissioners voted last month to sell T-5′s cranes, too small for the ships they want to expand it to handle

The commission still has steps to take before its modernization plan would be fully in gear – not the least of which would be, deciding how to pay for its likely nine-digit price. So in the meantime, interested citizens have unofficially suggested alternative futures for the site. One is on the agenda for the West Seattle Transportation Coalition’s meeting next Tuesday, 6:30 pm at Neighborhood House’s High Point Center, 6400 Sylvan Way, everyone welcome. The agenda also includes Q/A with new SDOT director Scott Kubly, who spoke with the Southwest District Council earlier this week, as covered here.

1 West Seattle ‘deletion’ in newest Metro bus-cut plan – with a caveat

September 2, 2014 at 11:46 pm | In Transportation, West Seattle news | 22 Comments

Metro‘s next round of proposed cuts went public this evening, a list of proposals to kick in next February. But they come with a big caveat – if Seattle voters pass the mayor’s transit-funding proposal in November, the February cuts would be postponed until June, and might not happen at all.

First: Here’s the official announcement, with this list-at-a-glance:

As you can see, a few West Seattle cuts are on the list: Route 22, already a shadow of its former self (it once went all the way downtown and is now just a circulator), would be deleted. Part of its service area would keep transit via a change in Route 125, whose proposed revised map looks like this:

Cuts/changes would be also be in store for Route 21, which would be reduced from 15-minute intervals on weekday middays and Saturdays to 30-minute intervals, and for Route 116X, which serves West Seattle on its way to/from the Vashon ferry, cutting three trips a day.

Metro/county reps who talked with WSB via phone conference tonight, after the release of this plan, say the full list of cuts proposed for February equals roughly half what was originally set to be cut through September of next year. And they point out that the West Seattle proposals reflect changes made after public comment on earlier proposals – for example, Route 50 is being left alone.

But passage of the transit money measure in November wouldn’t guarantee cancellation of these cuts – the city and county could work out a different set of buybacks, for example, maybe even involving changes to be made this month (not involving West Seattle routes). And they don’t know what would be needed in terms of belt-tightening after February cuts – that would be worked out in the county’s September 2015 budgeting.

For now, these proposals are expected to go to the County Council within the next two weeks, so that action would be finalized before the council’s focus turns to the budgeting process. Something to say about this new plan? West Seattle’s County Councilmember is Joe McDermott, whose contact info is here; he’s also the council’s current budget chair.

West Seattle Labor Day 2014: Here’s helpful holiday info

September 1, 2014 at 6:30 am | In Transportation, West Seattle news, WS miscellaneous | 3 Comments

(Photo by ‘Hammerin’ Man,’ shared via the WSB Flickr group)
Happy Labor Day! Just a few notes about the holiday …

TRAFFIC/TRANSIT/TRANSPORTATION INFO
Since many people are off work today, we’re not publishing the usual daily traffic/transit roundup. You can see area traffic cams and get info (including a link to the city map with travel times) on the WSB West Seattle Traffic page.

*Metro Transit is on a Sunday schedule
*West Seattle Water Taxi is on a Sunday schedule
*Sound Transit buses are on a Sunday schedule
*Washington State Ferries‘ Fauntleroy-Vashon-Southworth route will be on a weekend schedule

TRASH/RECYCLING PICKUP: If you are a Monday customer, SPU says it’s a normal pickup day.

SEATTLE PARKS: Here’s the citywide Parks lineup for what’s open/closed. Including:

LAST DAY FOR WADING POOL/SPRAYPARK: It’s the final day of the season for the last wading pool in operation, Lincoln Park, and for Highland Park Spraypark. Both are scheduled to be open 11 am-8 pm today. (If you go to the spraypark, you can explore astronomy too!) **9:46 am update: It’s not wading-pool weather, so the pools won’t open, and are done for the season, the city says, but adds that the sprayparks WILL open today.**

THIRD-TO-LAST DAY FOR COLMAN POOL: West Seattle’s outdoor pool, on the shore in Lincoln Park, ends its daily operations after today, with just one encore, the post-season September 6-7 weekend. So if you’ve been meaning to get to Colman, here’s the schedule.

LIBRARIES: It’s a systemwide closure day for the Seattle Public Library.

‘PARKING HOLIDAY’: Though West Seattle has no pay stations/meters on city streets, in the neighborhoods that do, this is a “parking holiday” – no charge.

BUSINESSES OPEN TODAY: Though we didn’t put out a general call for info, several businesses did take the time to message us with word they’re open (thank you!):

*Hotwire Coffee (WSB sponsor) – Open 7 am-6 pm
*The Bridge – Open for brunch, 9 am-2 pm “with both of our patios open” (and then open with regular menu until usual close)
*Pizzeria 22 and Quadrato – Both open regular hours
*Avalon Glassworks – Open 10 am-6 pm

EVENT CALENDAR: Quiet for the holiday, but you’re welcome to take a minute and browse ahead.

Fauntleroy ‘Boulevard’ plan update: Community meeting set for September 23rd

August 20, 2014 at 6:21 pm | In Transportation, Triangle, West Seattle news | 21 Comments

The date is now set for the promised community open house about the Fauntleroy Way SW Boulevard Project in The Triangle, currently in “early design,” tentatively scheduled for construction late next year if city leaders approve project funding: 5-7 pm Tuesday, September 23rd, is the date for that communitywide discussion of the project, proposed for Fauntleroy Way SW between 35th and Alaska. SDOT’s Maribel Cruz tells WSB they’ve had briefings in recent weeks with:

· Seattle Pedestrian Advisory Board
· Seattle Bicycle Advisory Board
· Freight Advisory Board
· Washington State Ferries
· West Seattle Transportation Coalition
· West Seattle Bike Connections
· West Seattle Junction Association

We were at the WSTC/WSBC briefing last month, along with one member of each of those groups. No major new details emerged, but the question that arose in comments on our July 15th report, “what about the Trader Joe’s onstreet loading zone?” was asked, and the reply was that they’re still discussing options. As a “boulevard,” that section of Fauntleroy will have “no loading zones and no parking,” the project team said.

Background on the project, as well as details of its status, are on the official SDOT webpage. The September 23rd meeting will be at the Senior Center of West Seattle (Oregon/California).

47th/Admiral signal: Design’s done; construction set for this fall

August 19, 2014 at 12:21 pm | In Safety, Transportation, West Seattle news | 64 Comments

SDOT has announced that design is done and construction will start this fall – possibly as soon as October – on the long-sought signal at 47th SW and Admiral Way, and that it will be accompanied by four striped crosswalks, as seen in the new design graphic above. This fall will mark three years since the Admiral Neighborhood Association ramped up its campaign for the signal with a rally in memory of 26-year-old Tatsuo Nakata, killed at the intersection in fall 2006. It took a lot of pushing to get funding committed – in early 2012, SDOT was still saying 47th/Admiral wasn’t high on the list. Then last year, the City Council made changes in then-Mayor McGinn’s spending plan in order to find full funding for the signal.

Here are key parts of the finalized plan, according to SDOT:

*Installing a new traffic signal
*Adding four additional striped crosswalks
*Upgrading six curb ramps at key corners of the intersection to be compliant with current American Disability Act (ADA) standards
*Replacing the existing center-turn lane with left-turn-only pockets on SW Admiral Way
*Removing minimal parking up to 50 feet from the intersection approaches on the north and south sides of 47th Avenue SW and SW Waite Street
*Removing the existing pedestrian signal

According to SDOT’s Maribel Cruz, “We anticipate construction will begin late this fall and will last for approximately three months, depending on weather conditions. The project team plans to host a community drop-in session at a nearby café in October, prior to the start of construction, and will continue to keep the community informed as the project progresses.” More information is online at this newly updated project page.

P.S. We should note that this intersection will be a lot busier soon, with Aegis Living planning to build a new retirement center on the 4700 SW Admiral Way site of the former Life Care Center, proposed to include 48 assisted-living apartments and 33 memory-care apartments..

Ferry-alert update: Fauntleroy-Vashon-Southworth back to 3 boats

August 18, 2014 at 12:51 am | In Transportation, West Seattle news | Comments Off

We noticed on Washington State Ferries‘ VesselWatch that the M/V Evergreen State, which broke down on Saturday, was back on the move as of earlier this hour – and now, WSF has sent official word that it’s back to the three-boat Fauntleroy-Vashon-Southworth for today’s morning commute:

Necessary repairs on the Evergreen State have been made and the route will return to the three boat schedule on Monday, August 18 beginning with the 4:05 am sailing from Vashon.

Without the Evergreen State, the “Triangle route” had been down to 2 boats all weekend, with long waits.

2-wheel tour: West Seattle Bike Connections ride with councilmember

August 17, 2014 at 12:09 pm | In Transportation, West Seattle news | 6 Comments

(At new Junction ‘bike corral,’ last stop on the tour)
West Seattle Bike Connections members spent part of their weekend taking City Councilmember Tom Rasmussen, who chairs the council’s Transportation Committee, on a tour “to get a first-hand look at some of the routes and intersections in the Seattle Bicycle Master Plan that we think are high priority for funding and implementation,” according to WSBC president Don Brubeck, who shares photos and this report from Saturday’s tour:

We started at Highland Park Improvement Club. First stop: The crosswalk at 11th Ave SW (a planned Greenway route) at SW Holden St, a busy arterial. We are supporting the Highland Park Action Committee’s application to SDOT for flashing beacons to help make this a safe crossing for kids going to schools and playgrounds in Highland Park and Riverview.

Then south on 10th Ave to SW Thistle at Highland Park Playfield. These are mapped as future Greenway routes, and seem ideal low traffic streets for walking and riding bikes. A set of public steps at 14th allows pedestrians to continue through on Thistle, but stops cars and bikes. We’d like to see a “runnel” gutter for bike wheels added to the steps, which are under construction now.

Then north on 17th Ave SW, which is a neighborhood Greenway route currently in the planning and design stage. The proposed route jogs over to 15th Ave on Kenyon, then back over to 17th at Webster. These jogs did not seem realistic to our group. Who would want to go 2 blocks east out of their way, and then 2 blocks west back to their route? And the intersections of Kenyon & 16th, 15th & Holden, and Webster & 16th would all need marked crosswalks and signals to be safe Greenway crossings. It looks much easier to just improve Holden for the short block from 17th to 16th, and then 16th to Webster, to get around the block that does not go through on 17th.

Click to read the rest of 2-wheel tour: West Seattle Bike Connections ride with councilmember…

Next Page »

All contents copyright 2014, A Drink of Water and a Story Interactive. Here's how to contact us.
Header image by Nick Adams. ABSOLUTELY NO WSB PHOTO REUSE WITHOUT SITE OWNERS' PERMISSION.
Entries and comments feeds. ^Top^