Followup: Where the dirt from overflow-control tank dig is going, and other questions answered

September 18, 2014 10:12 pm
|    Comments Off on Followup: Where the dirt from overflow-control tank dig is going, and other questions answered
 |   Environment | West Seattle news

One of West Seattle’s biggest digs is under way.

Excavation started today at the site of King County’s Murray Combined Sewer Overflow control project, a million-gallon underground tank across from Lowman Beach. The announcement published here Wednesday – noting that up to 55 trucks a day will travel two nearby routes – brought lots of questions in WSB comments, so we asked KCWTD’s Doug Marsano for answers. We also went to the site overlook along Lincoln Park Way for a firsthand look (see the short video above, and the photo added here).

HOW MUCH DIRT? At an earlier community meeting, it was described as “enough to fill Colman Pool twice.” Specifically, we now know – 21,000 cubic yards.

WHERE IS IT BEING TAKEN? Basically, east King County: “Cedar Hills Landfill at 16645 228th Ave SE, in Maple Valley, and Reserve Silica Corporation on Black Diamond Road in Ravensdale.”

ARE THE TRUCKING HOURS SAME AS THE WORK HOURS? The latter, according to this week’s update, are 7 am-6 pm. But, we learned today:

Haul hours are 8 am- 3:30 pm. There may be additional trucks entering or leaving the site outside of those hours, but the bulk of the trips will occur between during haul hours.

IS IT ‘UP TO 55 TRUCKS A DAY’ FROM THE START, OR RAMPING UP? The latter, replied Marsano: “Today, for instance, crews removed about 30 loads. The most intense period will be through early October when the tank hole is relatively shallow. Truck trips will slow to about 20 a day (or 3-4 an hour) when the hole is at its deepest.”

WHERE ARE THE TRUCKS STAGING? “The initial plan is to stage trucks on Fauntleroy. Adjustments will be made as necessary to ease congestion and accommodate ferry traffic, including use of 48th Ave and the east side of Beach Drive.”

The project website is here; the 24-hour project hotline, for questions or to report problems, is 206-205-9186. Current timeline for completing the storage-tank facility is the second half of 2016.

No Replies to "Followup: Where the dirt from overflow-control tank dig is going, and other questions answered"