While high-profile closures like the West Seattle “low bridge” and SB Highway 99 get all the attention, they’re not the only closures people are dealing with right now. For example, 35th SW between 104th and 106th remains closed for a fourth week in Arbor Heights, because of drainage work in the first phase of the 100th-to-106th sidewalk project. Today, the project team sent this update:

This week, our crews completed concrete pour at driveways and curbs along 35th Ave SW, between SW 104th St and SW 106th St. We tested the newly installed detention pipe and conducted any pipe repair work necessary to begin operation. We then backfilled and repaved the street surface.

Next week, our crews will begin sidewalk construction on the west side of 35th Ave SW, between SW 104th St and SW 106th St. We will coordinate with Puget Sound Energy to schedule for their crews to relocate the gas main at SW 106th St. We hope to complete the sidewalk construction for this segment of 35th Ave SW by the end of next week.

Since that didn’t include a progress report on the 35th closure, we asked about the latest estimate on when it’ll be over. The reply from project spokesperson Ching Chan: ” Assuming the sidewalk construction work on 35th goes smoothly next week, we are hoping to reopen the closed segment of 35th (between 104th and 106th) by first week of July.” An update is promised around the middle of next week.