ROAD WORK ALERT: Bicycle/pedestrian detours continue this week in Spokane Street project zone

August 28, 2016 3:49 pm
|    Comments Off on ROAD WORK ALERT: Bicycle/pedestrian detours continue this week in Spokane Street project zone
 |   Safety | West Seattle news | West Seattle traffic alerts

Tomorrow will be the start of the fourth week of work on SDOT’s lower Spokane Street project – happening mostly east of the “low bridge” – which the city says will “repave, reconstruct sidewalks and curb ramps, and make other improvements along SW Spokane Street from SW Klickitat Way to East Marginal Way S to improve safety for all users.” Below are key points from the overview of what’s planned this week, including continued detours for people on bikes and on foot:

SW Klickitat Way and Manning Street
– Forming and pouring new curb ramps and replacement portions of sidewalk.
– Roadway asphalt patching.

SW Spokane St and Manning St
– Reconstructing curb ramps and sidewalk on south side of Spokane St.
– Constructing a raised crosswalk in the West Seattle Bridge Trail across the driveway on the north side of Spokane St at Manning St

WHAT TO EXPECT DURING CONSTRUCTION FOR THE WEEK OF AUGUST 29, 2016
• Weekday work hours from 9 AM to 4 PM
• Single lane closures and/or lane width reductions during work hours
• Noise, dust and vibration typical of construction
• Access to the port and businesses will be maintained
• Temporary pedestrian/bike pathway around work zone at SW corner of Spokane St and 11th Ave SW
• Temporary pedestrian/bike pathway around work zone on north side of Spokane St at Manning Street

The project summary is on this SDOT webpage.

No Replies to "ROAD WORK ALERT: Bicycle/pedestrian detours continue this week in Spokane Street project zone"

    Sorry, comment time is over.